Forwards IE Insp Repts 50-010/80-07,50-237/80-07 & 50-249/80-10 on 800303-0404 & Notice of Violation
ML19323H935
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 04/24/1980
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML19323H936 List:
References
NUDOCS 8006170308
Download: ML19323H935 (2)


See also: IR 05000010/1980007

Text

-

.

- . . - - .

- . - . . . . . . . ~ - .

. . ~ . . . .

. . -

-

TIC

.

.n

'o,,

UNITED STATES

e

E

NUCLEAR REGULATORY COMMISSION

g

,

r,

a

REGION 111

0

'#

799 ROOSEVELT ROAD

GLEN ELLYN. lLLINOIS 60137

          • ,o

APR 2 4 880

.

Docket No. 50-10

Docket No. 50-237

Docket No. 50-249

Commonwealth Edison Company

ATTN:

Mr. Cordell Reed

Vice President

Post Office Box 767

Chicago, IL

60690

Gentlemen:

This refers to the inspection conducted by Messrs. J. L. Barker and

T. M. Tongue of this office on March 3 through April 4,1980, of activ-

ities at Dresden Nuclear Power Station; authorized by NRC Operation

License No. DPR-2, DPR-19 and DPR-25 and to the discussion of our find-

ings with Mr. B. B. Stephenson and others of your staff.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of a

selective examination of procedures and representative records, observa-

tions, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, as described in the enclosed

Appendix A.

The inspection showed that action had been taken to correct

the identified noncompliance and to prevent recurrence.

Consequently, no

reply to this noncompliance is required and we have no further questions

regarding this matter at this time.

In accordance with Section 2.790 of the NRC'u " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room, except as follows.

If this report contains information that you or

your contractors believe to be proprietary, you must apply in writing to

this office, within twenty days of your receipt of this letter, to with-

hold such information from public disclosure. The application must

include a full statement of the reasons for which the information is con-

sidered proprietary, and should be prepared so that proprietary informa-

tion identified in the application is contained in an enclosure to the

application.

80 06170 '30 f

.

. . . .

. _ .

-

=..

..

,

P

i

Commonwealth Edison-Company

-2-

APR 2 4 EE0

.

We will gladly discuss any questions you have concerning this

inspection.

Sinc

y,

O

. F. Heishman, Chief

Reactor Operations and

Nuclear Support Branch

Enclosures:

1.

Appendix A, Notice of

Violation

2.

IE Inspection Report No.

50-010/80-07, No. 50-237/80-07

,

'

and No. 50-249/80-10

cc w/encls:

Mr. D. L. Peoples, Director

of Nuclear Licensing

Mr. B. B. Stephenson,

Station Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

'

Mr. Dean Hansell, Office of-

Assistant Attorney General

.

--

. - .