ML19323E602
| ML19323E602 | |
| Person / Time | |
|---|---|
| Site: | Quad Cities |
| Issue date: | 04/14/1980 |
| From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | |
| Shared Package | |
| ML19323E600 | List: |
| References | |
| 50-254-80-08, 50-254-80-8, 50-265-80-01, 50-265-80-1, NUDOCS 8005270037 | |
| Download: ML19323E602 (1) | |
Text
r Appendix A NOTICE OF VIOLATION Commonwealth Edison Company Docket No. 50-265 Based on the inspection conducted on March 9-11, 1980, it appears that one of your activities was in noncompliance with NRC requirements, as noted below. This item is a deficiency.
Technical Specification 6.2.A requires that " Detailed written procedures including applicable checkoff lists....shall be prepared, approved, and adhered to."
Contrary to the above, Procedure QTS 150-57, Revision 6, " Unit 2 IPCLRT Valve Lineup," was not adhered to in that valve position verfication was not carried out on March 8, 1980, to verify that Valves 2-1402-33A and 2-1402-33B (local leak test valves for core spray isolation valves) were locked closed as required.
8005270039 e
Q
- - -