MONTHYEARML19323C2861980-03-28028 March 1980 EN-80-010:on or About 800331,confirmatory Orders Will Be Issued to Licensees to Formalize Commitment Re Responses to IE Bulletin 79-27.Licensees Deferred Completion of Bulletin Review Beyond 800401 Project stage: Request ML19340D1641980-12-20020 December 1980 Forwards Response to Applicable Requirements of NUREG-0737 Re TMI Action Plan.Progress of Response Impeded Due to Lack of Guidance Re Applicability of Requirements to Gas Cooled Reactor Project stage: Other ML20010E9871981-08-26026 August 1981 Forwards Update of Various NUREG-0737 Requirements Delineating Status of Items in Order to Clarify Implications of NRC 810806 Order.Since Facility Is Gas Cooled,Some Requirements Inapplicable Project stage: Other ML20063N2591982-07-30030 July 1982 Provides Updated Status Rept of NUREG-0737 Action Items,Per Request Project stage: Other ML20071Q5751982-11-18018 November 1982 Forwards Response to Telephone Inquiries Re Status of NUREG-0737,Item III.D.3.4, Control Room Habitability Project stage: Other ML20023C4961983-04-29029 April 1983 Informs That Control Room HVAC Sys Satisfies Requirements of single-failure Criteria for Control Room Habitability.No Further Mods Anticipated Project stage: Other ML20076C9371983-07-28028 July 1983 Responds to NRC 830711 Telcon Request for Addl Info Re Control Room HVAC Failure Criteria.Five Dampers Identified W/More Conventional Dv Damper Valve Nomenclature.Corrected List of Valve Identification Numbers Encl Project stage: Request ML20084L1391984-05-0303 May 1984 Advises That No Postulated Accident Condition Exists That Will Result in Present Noble Gas Radiation Stack Monitors Going off-scale Per TMI Item II.F.1.Evaluation Re Obtaining Permanent Monitor Will Be Submitted in 60 Days Project stage: Other ML20093A4761984-07-0202 July 1984 Describes Action Plan in Response to 840403 Concerns Re NUREG-0737,Item II.F.1.1, Noble Gas Accident Monitoring Instrumentation. Reactor Plant Exhaust Stack Discharge Will Be Diluted by Using Clear Source of Air Prior to Release Project stage: Other ML20093K1261984-07-12012 July 1984 Clarifies Mid to Late 1985 Commitment Date for Mod of Reactor Plant Exhaust Stack Noble Gas Radiation Monitoring Sys.Mod Will Be Complete Prior to End of Fourth Refueling Outage,Per NUREG-0737,Item II.F.1.1 Project stage: Other ML20101C2671984-11-28028 November 1984 Discusses Replacement of Existing Reactor Plant Exhaust Detector W/Extended Range Monitor Per TMI Item II.F.1.1. Replacing Existing Detector W/Higher Range Monitor More Desirable than Dilution Sys Due to Simplified Design Project stage: Other ML20126A9461985-05-17017 May 1985 Forwards Plan for Installation of Dilution Sys Per NUREG-0737,Item II.F.1.1.Dilution Factor Discussed. Continuous Remote Readout & Alarm Will Remain in Control Room.Sys Will Be Installed by Fourth Refueling Outage Project stage: Other 1983-04-29
[Table View] |
EN-80-010:on or About 800331,confirmatory Orders Will Be Issued to Licensees to Formalize Commitment Re Responses to IE Bulletin 79-27.Licensees Deferred Completion of Bulletin Review Beyond 800401| ML19323C286 |
| Person / Time |
|---|
| Site: |
Hatch, Browns Ferry, Salem, Indian Point, Oyster Creek, Sequoyah, Surry, North Anna, San Onofre, Yankee Rowe, Fort Saint Vrain |
|---|
| Issue date: |
03/28/1980 |
|---|
| From: |
Jordan E, Wilber H NRC OFFICE OF INSPECTION & ENFORCEMENT (IE) |
|---|
| To: |
|
|---|
| References |
|---|
| EN-80-010, IEB-79-27, NUDOCS 8005150279 |
| Download: ML19323C286 (2) |
|
Similar Documents at Hatch, Browns Ferry, Salem, Indian Point, Oyster Creek, Sequoyah, Surry, North Anna, San Onofre, Yankee Rowe, Fort Saint Vrain |
|---|
|
Text
SA a
4 March 28, 1980 g j\\ d. 1 Ih "MTIFICATICN OF SIGrilFICANT E:
M D b
4FORCEMENT ACTION OFFICE OF INSPECTION AND ENFORCEMENT EN-80-10 O GN D h
^
E00515 0.279 Licensees:
As listed belos
Subject:
CONFIRMATOP.Y ORDERS FOR LICENSEES' RESPONSES TO IE SULLETIN 79-27 This is to inform the Commission that Confirmatory Orders are being issued on er about March 31, 1980,' to 10 licensees for 18 facilities to formalize commit-ments from the licensees to respond to IE Bulletin 79-27 by specified dates.
These licensees had deferred their completion of the review of the Bulletin beyond April 1,1980, which is over 30 days after tne assigned date of the response in the Bulletin.
The licensees and f*.cilities are as follows:
Tennessee Valley Authority Browns Ferry No. 1 Browns Ferry No. 2 Browns Ferry No. 3 Sequoyah No. 1 Vircinia Electric and Power Comoany North Anna No. 1 North Anna No. 2 Surry No. 1 Surry No. 2 Georgia Pcwer Company Hatch No. 1 Hatch No. 2 Public Service Electric and Gas Company Salem No. 1 Salem No. 2 Power Authority of the State of New York Indian Point 3 Consolidated Edison Company of New York Indian Point 2 Jersey Central Power and Licht Company Oyster Creek Yankee Atomic Electric Comoany Yankee Rowe CONTINUED
ContinuGd EN 10 Page 2 Public Service Comoany of Colorado Fort St. Vrain Southern California Edison Comoany San Onofre Unit No. 1
Contact:
HAWil"-
IE x28180 ELJordan, IE x28180 Distribution:
Transmitted H St 2b'. 3d5>'
Chairman Ahearne Commissioner Hendrie S. J. Chilk, SECY Commissioner Gilinsky Commissioner Bradford C. C. Kammerer, CA Commissioner Kennedy ACRS (For Distribution)
Transmitted:
MNB8 lb'.5I:
P. Bldg ZE:63 V. Stello, IE W. J. Dircks, EDO H. R. Denton, NRR Region I fst o /
C. Michelson, AE00 R. J. Mattson, NRR Region II 5": ro J. J. Fouchard, PA D. Vassallo, NRR Region III 5 : e4-N. M. Haller, MPA D. Eisenhut, NRR Region IV _{d fg(:
R. G. Ryan, OSP Region V 5 :e F H. K. Shapar, ELD SS Bldg U.57 J. G. Davis, NMSS LandowSectSf?s S. Levine, RES J. J. Cummings, 01A (MAIL)
R. Minogue, 50 PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL 4/2/80 f
s 9
g