ML19323B124

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-373/80-08 & 50-374/80-04 on 800130-31,0201, 04 & 07.Noncompliance Noted:Failure to Revegetate Affected Area of East Face of East Dike in Timely Manner
ML19323B124
Person / Time
Site: LaSalle  
Issue date: 03/07/1980
From: Essig T, Oestmann M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19323B121 List:
References
50-373-80-08, 50-373-80-8, 50-374-80-04, 50-374-80-4, NUDOCS 8005090471
Download: ML19323B124 (9)


See also: IR 05000373/1980008

Text

80 On a g n yy,

U.S. NUCLEAR REGULATORY COMMISSION

.

OFFICE OF INSPECTION AND ENFORCMENT

REGION III

Report Nos. 50-373/80-08; 50-374/80-04

Docket Nos. 50-373; 50-374

License Nos. CPPR-99; CPPR-100

Licensee:

Commonwealth Edison Company

P.O. Box 767

Chicago, IL 60690

Facility Name:

LaSalle County Nuclear Station, Units 1 and 2

Inspection At: LaSalle Site, Seneca, IL (January 30-31, February 1, 7, 1980)

Commonwealth Edison Company Corporate Office (February 4, 1980)

Inspection Conducted: January 30-31, February 1, 4, and 7, 1980

'fN.C.CA b w w

-,

Inspector:

M. J. Oestmann

h-

wW

Approved By:

T. H. Essig, Chief

k7[So

Environmental and Special

Projects Section

Inspection Summary

Inspection on January 30-31, and February 1, 4, 7, 1980 (Report

Nos. 50-373/80-08; 50-374/80-04)

Areas Inspected: Routine, announced inspection of environmental pro-

tection for Units 1 and 2, including implementation of construction

permit requirements; nonradiological environmental monitoring programs;

status of item of noncompliance and open items identified in previous

inspections; an investigation of cooling lake blowdown line rupture and

subsequent environmental impact. of blowdown corridor and adjacent farm-

land. The inspection involved 35 inspector-hours on site by one NRC

inspector.

Results: Of the areas inspected, no apparent items of noncompliance or

l

deviations were identified in two areas; one apparent deviation was

identified in one area (failure to revegetate the affected area of the

'

east face of the east dike in a timely manner - Paragraph 2a).

l

l

1

i

r

,

.

DETAILS

,

.

1.

Persons Contacted

i

Principal Licensee Personnel

.

.

  • C. McDonough, Assistant to the Director of the Environmental

l

-

Affairs Department (EAD), CECO

  • R. Montzingo, Staff Biologist (EAD), CECO

J. Golden, Administrator, Radiological and Envircnmental Monitoring

Program, Production and Systems Analysis Department (PSAD), CECO

j

L. Burke, Site Project Superintendent, LaSalle County Nuclear

Station (LSCS)

J. Gutierrez, Environmental Site Coordinator, LSCS

B. Wood, Quality Assurance Engineer, LSCS

    • R. Holyoak, Plant Superintendent, LSCS
    • W. Huntington, Lead Special Projects Engineer, LSCS
    • G. Reardanz, Quality Assurance Engineer, LSCS

J. Ullrich, Engineering Assistant, LSCS

F. Lawless, Rad / Chem Supervisor, LSCS

    • J. Bruciak, Engineering Assistant. LSCS

Other Personnel

D. Bedeker, tenant farmer of adjacent farmland owned by

Mr. H. Killelea and Mrs. F. Nessinger

R. Engel, owner of farmland adjacent to blowdown corridor.

  • Denotes those present at the corporate exit interview on February 4,

1980.

    • Denotes those present at the plant exit interview on February 7,

1980.

The inspector also interviewed several other licensee employees

during the course of the inspection, including health physics and

chemistry technicians, members of the construction and security

force, and general office personnel.

2.

Licensee Action on Previous Inspection Findings

(0 pen) Noncompliance (50-373/78-05, 78-22, 79-05, 79-20;

a.

50-374/78-05, 78-16, 79-03, 79-14): Failure to minimize

erosion of the east dike of the cooling lake. The inspector

discussed with licensee representatives the status of the

environmental monitoring program regarding vegetative cover

of the dikes and the dredging and seeding of the Armstrong

-2-

r

.

Run, described as part of the five requirements on page 4-6

.

in the FES-OL. The licensee committed to meeting these fiv

requirements as discussed in a previous inspection report. gj

The inspector reviewed the 1979 environmental inspection re-

ports of the cooling lake dike conducted by the licensee's

contractor, Sargent and Lundy, in accordance with requirement

2.

In January 1979, the contractor recommended re-seeding the

-

exterior dike from approximately the station 140 to 156; in

May 1979, the contractor found little or no vegetation at Sta-

tion 76; in August 1979, an area on the east dike between Sta-

tion 154 and Station 170 had little or no crown vetch, rather

it contained weeds, clover, and rye grass.

The inspector

found that re-seeding of the dike between Stations 96 to 99,

140 to 141, and 174 to 176 had been completed in August 1979

by the Walsh Construction Company, a licensee contractor.

In

October 1979, the inspector toured the cooling lake and noted

that certain sections of the east face of the dike required

additional seeding. This was co

spection conducted in May 1979. g rved during a previous in-

At that time, the licensee

informed the inspector that he had planned to re-seed the dike

wherever it was needed during June 1979.

In reference to re-

quirement 3, the licensee did not re-vegetate, particularly

with crown vetch, the affected area along stations approxim-

ately 145 to 200 in a timely manner, in 1979. This is a de-

viation from the licensee commitment.

In reference to requirements 4 and 5, the inspector determined

the Armstrong Run had been dredged last fall in 1979, by the

landowner's contractor, T. T. K. Enterprises. The inspector

discussed the seeding of banks of the run with the tenant

farmer, Mr. Bedeker. He plans to seed the banks in April and

May 1980.

Thisitem[87ainsopen,pendingcompletionofthelicenseecom-

3

mitments

to take actions discussed in Items 3, 4, and 5 of

the FES-OL.

The above areas will be reviewed during a future

inspection.

b.

(0 pen) Significant Inspection Finding (50-373/78-26, 79-05, 79-20):

Complet on of emergency planning implementing procedures (LZP's).

Several LZP's identified in Inspection Report No. 50-373/79-20

remain to be completed prior to the licensee receiving a fuel

load license. The licensee's emergency plan, the Generating

Station Emergency Plan, and Annexes and LPZ's are being revised

1/ IE Inspection Report Nos. 50-373/79-05; 50-374/79-03.

2/ IE Inspection Report Nos. 50-373/79-20; 50-374/79-14.

3_/ Letter, M. Turbak (CECO) to V. A. Moore (NRC), dated March 16, 1978.

4_/ Letter, C. Reed (CECO) to V. A. Moore (NRC), dated May 25, 1978.

-3-

__

.

in light of changes in emergency planning requirements by NRC.

This item remains open, pending approval of the revised GSEP,

Annexes and LPZ's by NRC.

(0 pen) Significant Inspection Finding (50-373/79-05; 50-374/79-03):

c.

Completion of the licensee's quality assurance and qual,ity con-

trol of analytical measurements and measurements capability test

-

for confirmatory measurements inspection program. The inspector

discussed the status of the chemistry and radiochemistry program

with licensee representatives. A tour of these facilities was

made during this inspection. The facilities are being equipped

with counting equipment. Once the equipment is calibrated the

licensee will be ready to accept radioactive samples for count-

ing and to test his analytical capability within the next several

months pursuant to the NRC's Confirmatory Measurements Program.

His analytical procedures also should be completed at that time.

This item remains open, pending completion of the Confirmatory

Measurements Program prior to fuel load license.

3.

Management Controls

The inspector examined the licensee's management of the preopera-

tional nonradiological environtental monitoring programs and im-

plementation of environmental protection practices to assure com-

pliance with Construction Permit requirements. The management

control aspects, including organizational responsibilities, de-

legation of authority, and adminstrative procedures, have remain

thesameasdescribedinthepreviousenvironmentalinspection.gp

-

The inspector reviewed a site quality instruction prepared by the

licensee's Quality Assurance Department, to assure that the con-

struction management sign-off the daily, monthly, and bi-monthly

environmental protection check sheets in compliance with their

Construction Permit environmental procedure. This directive, dated

June 4, 1979

inspection. 6/w s in response to an item discussed in a previous

The inspector has no further questions regarding

this matter.

The inspector discussed with licensee representatives the adminis-

trative controls which the licensee needs to implement in order to

meet the five licensee commitments discussed on page 4-6 of the

Final Environmental Statement and in References 3 and 4 in this

inspection report. The licensee agreed to prepare management in-

structions to implement and comply with the commitments in the

FES-OL. This remains as an open item and will be examined during

a subsequent inspection.

5/ IE Inspection Report No. 50-373/79-20; 50-374/29-14.

6/ Ibid.

l

-4-

.

The inspector reviewed licensee internal documentation which re-

ported the management of the Haileton contract for the aquatic and

terrestial monitoring program by the Environmental Affairs Depart-

ment.

Thi was in response to an item discussed in a previous in-

spection. 9j A five year environmental program was completed in

1978 and the fifth annual report was issued in 1979. The inspector

i

.

has no further questions regarding this matter.

No apparent items of noncompliance or deviations were identified.

4.

Licensee Internal Audits

The inspector examined the check sheets for calendar year 1979,

used to comply with the Construction Permit environmental pro-

tection requirements. This sheet is completed by the Environmental

Site Coordinator, either on a daily, monthly, or bi-monthly basis.

The check sheets were found to be reviewed by the licensee's Quality

Assurance Department and construction management, in accordance with

an established environmental protection procedure. The Environmental

Affaf:s Department also reviewed the monthly and bi-monthly check

sheets in accordance with the same procedure. This review and audit

of the check sheets by site management and the Environmental Affairs

Departmentarein7esponsetoanitemdiscussedinapreviousin-

spection report. 8 The inspector has no further questions regard-

ing this matter.

No apparent items of noncompliance or deviations were identified.

5.

Implementation of the Preoperational Monitoring Program for Environ-

mental Protection

a.

Implementation of the Ecological Monitoring Program

The licensee issued its fifth annual report in 1979 for the

five year aquatic and terrestial ecological monitoring program

completed in 1978.

This program was conducted by the licensee's

contractor, Hazleton Laboratory from 1974 to 1978. The licen-

see's contractor conducted studies of phytoplankton, and its

physiology, periphyton, zooplankton, macroinvertebrates, and

fisheries in the aquatic program. No apparent construction

effects were evidenced on aquatic life in the Illinois River and

the South Kickapoo Creek. The terrestial program showed that

minor effects such as avian breeding resulted from construction.

The cooling lake attracted large numbers of water fowl. This is

the most significant plant construction - related effect on local

7/ IE Inspection Report Nos. 50-373/78-05; 50-374/78-04.

8/ IE Inspection Report Nos. 50-373/79-20; 50-374/79-14.

!

-5-

1

!

!

.

wildlife populations noted,during the study. The study also show-

ed that revegetation of the blowdown corridor, particularly slop-

ing areas crassing the bluff, was proceeding slowly.

Seeding of the make-up and blowdown corridor, using a grass legume

seed mixture was completed on October 13, 1979. The inspector ex-

amined the blowdown corridor on October 18, 1979, and found the area

had been seeded and hay laid down to hold the seed. Fences were

installed to restrict recreational traffic.

No significant problems

.

were identified at this time.

b.

Rupture of Blowdown Pipe

On January 25, 1980, during adjustment of the Howell-Bunger

valve on the cooling lake blowdown pipe, the 66-inch blowdown

pipe ruptured upstream of the valve. A hole in the ground

40 x 60 feet resulted. Water from the pipe flowed down ravines

on the licensee's property along the blowdown corridor and into

the Illinois River. Some of the water flowed into a ditch which

overflowed onto a driveway of farmland owned by Mr. Engel, caus-

ing some erosion of his property. The licensee has offered to

pay for any property damage.

On January 30, 1980, the inspector observed a bulldozer remov-

ing and excavating earth on top of the blowdown pipe.

Photo-

graphs of the excavation operation were taken. The inspector

also contacted the farmland owner, Mr. Engei, and discussed the

damage to his property. The licensee plans to dredge the ditch

and repair the driveway and farmland in early spring. This

item will be examined during a future inspection.

The licensee is conducting an investigation of the cause of

the rupture, believed to result from a water hammer effect.

The licensee is to sutmit to the NRC, a copy of the investi-

gation report and a pian of action to be taken to eliminate

or significantly reduce the detrimental effects or damage,

in accordance with Section 3.E(2) of the Construction Permit.

This item was discussed at the exit interview and will be ex-

amined during a subsequent inspection.

The inspector also discussed with licensee representatives,

,

'

the licensee's capability to isolate the cooling lake in the

event of a future rupture. During this particular pipe rupture,

the cooling lake was isolated by closing the butterfly valves

on the blowdown line in the valve house near the north side of

the cooling lake dike. The licensee can also regulate and iso-

late the blowdown flow, normally 45,000 gpm, from the cooling

lake by means of the Armco gates located on the blowdown channel,

at a point before the blowdown line goes under the cooling lake

service spillway. The inspector has no further questions re-

garding this matter.

i

-6-

.

s

c.

Fog Monitoring Program

.

The licensee has initiated a fog monitoring program described

in a letter to the NRC from the licensee, on January 2, 1980.

The licensee's meteorological contractor, Murray and Trettle

Incorporated, has trained four plant personnel to condu.ct the

visual observations for the fog monitoring program. The in-

-

spector discussed with the licensee representatives whether a

plant procedure would be prepared to implement this program.

No decision was made regarding this matter.

This item will

be examined duriag a subsequent inspection.

d.

Cooling Lake Monitoring Program

This program, described in Section 6 of the FES-OL, will be

initiated in the summer or fall of 1980, when it is anticipated

that plant construction will be completed and pumping of the

water through the circulating water system will begin. This

item will be reviewed during a future inspection.

e.

Ground Water Monitoring

The inspector examined records for CY-1979 of ground water

level of 20 observation wells installed in the vicinity of

the cooling lake.

-

The licensee has prepared a cooling lake dike inspection pro-

cedure (LTS-1000-5) for checking the seepage from the lake and

assuring the integrity of the cooling lake dike. The inspector

also reviewed a report, dated November 1, 1979, from Harza

Engineering Corporation which discussed the results of water

elevations in the observation wells, settlement monitoring of

the dike, and dike integrity. No particular problems were

identified.

f.

Environmental Protection Requirements

The inspector reviewed the environmental protection program

which has been implemented by the licensee in accordance with

Construction Permit requirements. Review of the daily, month-

ly, and bi-monthly check sheets for CY 1979, completed by the

Environmental Site Coordinator, indicated a need for re-seeding

of the south end of the blowdown corridor on November 14, 1979.

The initial seeding of the makeup and blowdown corridor was com-

pleted on October 13, 1979. After the repairs of the blowdown

line rupture discussed above in Paragraph 5.b, the licer.see will

re-seed these sections requiring seeding. This item will be ex-

amined during a subsequent inspection.

l

-7-

l

l

L

.~

.

As discussed in Paragraph 2a above, the inspector reviewed the

status of the environmental monitoring program regarding veget-

ative cover of the dikes, and dredging and seedingof the Arm-

strong Run.

In reference to requirement 1, described on page

4-6 in the FES-OL, the licensee contractor, Hazleton Laboratory,

prepared a second annual report on November 15, 1979, i,n which

the contractor conducted a quantitative measurement of vegeta-

tive cover of the dikes. The results indicate average vegeta-

-

tive cover ranges from 75.7% in May to 73% in August 1979. The

predominant vegetative cover is crown vetch (up to 50%), follow-

ed by annual, biennual, perennial volunteer species, primarily

weeds. The inspector discussed, with licensee representatives,

her concern regarding the poor vegetative cover on the east face

of the east dike also discussed in Paragraph 2a above. These

items will be reviewed in a subsequent inspection.

g.

Radiological Environmental Monitoring Program (REMP)

The inspector discussed with licensee representatives, the

collection of fish for the REMP. The licensee has obtained

Ecological Analysts as a sub-contractor to collect and provide

fish samples to the Eberline Instrument Corporation, for radio-

analysis in accordance with the licensee

REMP. This item

wasdiscussedinapreviousinspection.j7 A review of data on

fish sampling and analysis for CY 1979 indicates all analyses

were completed. The inspector has no further questions regard-

ing this matter.

A licensee representative also reported that in the future the

licensee's Quality Assurance Department will conduct all quality

assurance audits of the REMP contractor performance rather than

the adminstrator of the REMP program and his associates in PSAD.

No apparent items of noncompliance were identified. One devia-

tion was identified in reference to the poor vegetative cover

on the east face of the east dike and discussed in Paragraph

2.a.

6.

Exit Interview

The inspector met with licensee representatives denoted in Paragraph

1 at the conclusion of the inspection on February 4,1980, at the

corporate headquarters, and February 7, 1980, at the plant. The in-

spector summarized the purpose and the scope of the inspection, and

the findings. The licensee representatives made the following re-

marks:

9/ Ibid.

.

-8-

,

a.

Acknowledged that additional seeding with crown vetch was

o

needed on the east face of-the east dike and agreed to reseed

this area during the planting season in the spring of 1980

(Paragraph 2.a.)

b.

Discussed and would prepare an investigation report per,taining

to the blowdown pipe rupture, and submit a copy of the report

-

to the NRC as soon as possible.

(Paragraph 5.b.)

.

1

e

a

-9-

.

.

.

-

.

.