ML19322A701

From kanterella
Jump to navigation Jump to search
Testing & Startup Insp Rept 50-269/71-09 on 711012-15 & 1103.Noncompliance Noted:Failure to Review Adequacy & Status of QA Program,Failure to Prevent Overloading Cable Trays & Failure to Correct Weld Deficiencies
ML19322A701
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 02/10/1972
From: Moseley N, Murphy C, Swan W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19322A700 List:
References
50-269-71-09, 50-269-71-9, NUDOCS 7911210746
Download: ML19322A701 (15)


See also: IR 05000269/1971009

Text

_ _ _ _- - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

.

%

UNITED STATES

[ h

'5

ATOMIC ENERGY COMMISSION

g

I el

e

e

l

DIVISION OF COMPLIANCE

REGION 11 - SulT E 818

g

2M PE ACHT REE STREET, NORTHWEST

Ts6spesons: 4404)924-4903

v

AT LANT A. GEORGI A 30303

TESTING AND STARTUP INSPECTION REPORT

C0 Report No.: 50-269/71-9

Duke Power Con:pany

Oconee 1

Docket No. 50-269

License No. CPPR-33

Category A3/B1

Seneca, South Carolina

Type of Licensee : PWR-2452 MW(t), B&W

Type of Inspection: Routine, Announced

Dates of Inspection: October 12-15, 1971

Noveder 3,1971

Dates of Previous Inspection: Septes er 7-10, 1971

Principal Inspector:

J/7 JP

C. f. Muhphf, R%ctor Inspector (Testing

hie

and Startup)

,

h//0/7L

N. C. Moseley, Senior factor Inspector

Date'

(Testing and Sta.

p)

Accompanying Inspectors :

d

L

02/7F

W. Bi Swan, Reactor Inspector

Date

(Construction)

1 7 /.d'.d

ahh.2

R. L. Cubitt , Reactor Inspector

Dste'

~

(Operations)

$

.]h IV

W

, i

H. L. Whitener, heactor Inspector

  1. a t'e

D

(Operations)

-Y911210ft/f

.

i

_.

. _ , . _ _ . .

_

. - . . . . . . .

.

$

.

km

1-l1l9 V

W. W. Peery, RaR ation Specialist

Date

Other Accompanying Personnel: None

/0/7L

Reviewed By:

,

N. C. Moseley, Senior Reac[r Inspector

Date'

(Testing and Startup)

,

Proprietary Information: None

j

i

i

,

f

4

m

4

S

-

-

r ., --

n

-

.-

r

.

. - -

. .-

-

-

-

'

.

.

.

s.

C0 Report No. 50-269/71-9

-3-

SECTION I

Enforcement Action

A.

Noncompliance Items

1.

Criterion II of Appendix B to.10 CFR 50.- Failure to review

the adequacy and status of the quality assurance program.

(See Section II, Paragraph 7.)

-

2.

Criterion.XVI of Appendix.B.co.10.CFR 50 - Failure to take

corrective action to prevent continued overloading of cable trays.

(See Section II, Paragraph 6.)

.

3.

Criterion XVI.of Appendix.B.to 10 CFR 50 - Failure to correct

weld procedure deficiencies.

(See Section II, Paragraph 7.)

Licensee Action on Previously Identified Enforcement Matters

,

The licensee requested and received a two-week extension in which

to reply to the items of noncompliance. discussed in C0 Report No. 71-7,

datt d October 21, 1971. The response was due on November 15, 1971.

Unresolved Items

Failure to document corrective actions.

(See Section II, Paragraph 4.)

.

i

.

--

. - . - -

.

- .

--

,

.

'

.

'

.

'

CO Report No. 50-269/71-9

_4_

Status of Previously Reported Unresolved Items

i

A.

The licensee plans to verify the wall thickness of all accessible

Crane-Chapman valves. Crane-Chapman will be centacted by the licensee

'

in an attempt to determine a resolution to the potential problem with

Limitorque valve operators.

(See Management Interview.)

B.

Correction of the turbine building welding is underway.

.

1

C.

The licensee has sent a report to the Division of Reactor Licensing

discussing the control rod drive problem and their proposed corrective

action.

'

a

D.

The licensee is instituting a training program to upgrade the

'

site construction staff's familiari6y with the applicable codes

and regulations.

Unusual Occurrences - None

Persons Contacted

l-

4

Duke Power Company

l

W. S. Lee - Senior Vice President, Engineering and Construction

'

A. C. Thies - Senior Vice President, Production and Transmission

J. E. Smith -Superintendent, Oconee Station

J. C. Rogers - Project Engineer, Oconee and McGuire

D. G. Beam - Assis tant Project Engineer, Oconee

D. L. Freeze - Principal Field Engineer

J. W. Hampton - Assistant Superintendent, Oconee Station

M. D. McIntosh - Reactor Engineer

R. M. Koehler - Technical Support Engineer

L. E. Summerlin - Staf f Engineer

Management Interview

A. - Site

The following subjects were discussed with Smith, Brown, .Koehler,

Summerlin, Thames , Bradham, Wyke, - Beam, and Freeze at the Management

Interview on October 14, 1971.

,

,

t

4

r

-

.J ,

c-

. . - - . - -

-

- - - -

.

-

.

.

l

I

'

C0 Report No. 50-269/71-9

-5-

1.

The inspector advised Beam that the procew. ?-

for the use of

Variation Notices, Form QR-1, did not provide a method to assure that

Beam and W' ke agreed to

affected design drawings would be corrected.

y

initiate action to correct this deficiency.

2.

The inspectors advised Smith and Beam that in the audit of the

QC records, the inspectors had found references to problems

without corresponding references to the resolution of the problems.

The inspectors will provide Duke with a. list of these records and

examples of the problems and Duke.will be expected to document the

resolution of all problems contained in these records. Smith and

Beam agreed that this would be done.

(See Section II, Paragraph 4.)

3.

The inspector stated that.it was his understanding that Operations

was in .iating a work order system by.which the shift supervisor will

identify the problems appearing in the logs and issue a work order for

each -p roblem.

A. leg entry will be made in the. log referencing the work

order number.. .The work orders will. be kept in a suspense file until

cleared. They will. then. go .in. the. permanent.QA. file. This system will

.be.initiaten.rithin approximately . thirty days . . . Smith concurred in the

inspector's understanding.

(See Section II, Paragraph 5.)

4.

The inspectors advised Beam that. contrary.co the letter Compliance

had. received. from. Duke stating.that 12o cables .would.be pulled into

. overfilled . trays , . a review.of the . cable. pulling sheets . revealed that

. additional. cable.had.been pulled.in these . trays. .The. failure to take

corrective. action appeared to be. contrary to the. requirements of

Criterion XVI of Appendix B to 10 CFR 50.

(See Section II, Paragraph 6.)

5.

The inspector advised Beam.and . Freeze , that . contrary to the requirements

of Criterion II of. Appendix B to.10 CFR 50, his discussions with the

field. engineers. indicated that management had not conducted supervisory

7 -

. reviews o f . their . QA/QC . functions .

(On October 19, 1971, the inspector

received a telecon from Freeze in which he stated that a program of

reviews had been instituted.)

6.

Wyke advised the inspector.that the licensee.would measure the wall

thickness of _ those Crane-Chapman . valves . that were accessible.

In

addition, he would . meet .with Crane-Chapman on.che Limitorque problem.

In response to Wyke's questions, . the inspector advised Wyke that his

present. instructions were that he should seek to get a commitment for

the measurement of the wall thicknesses of all the valves in question.

_

-

..

.

, -

CO Report No. 50-26"/71-9

-6-

7.

The inspector advised Rogers and Beam that the failure to correct

the welding procedures appeared to be contrary.to the requirements of

Criterion XVI of Appendix B to 10 CFR 50. The inspector was advised

by Freeze that the procedures would be corrected within four weeks.

(See Section II, Paragraph 7.)

B.

Corporate Office

A second management interview was held at the Duke Power Company

corporate offices on November 3,1971, with Lee and Thies. The purpose

of this meeting was to discuss the failure of Duke to observe the quality

assurance criteria of Appendix B to 10 CFR 50. Moseley reviewed the

role of Compliance in auditing the licensee's operations to ensure

that the licensee observed the requirements of the . applicable codes,

license conditions, and regulations. Murphy .then discussed in detail

the . deficiencies .found by Compliance . inspectors.in the licensee's

implementation of Appendix B.

. Murphy pointed out the repetitive

nature of the deficiencies and stated that this was indicative of the

failure.of management to properly audit the work _being done and also

was . indicative of poor . communication up .through the management structure.

Lee indicated that steps .would be taken_ to. strengthen the licensee's

quality assurance. program and stated.that management changes were

planned for December 1971 that should help eliminate.the types of

deficiences described by Murphy. Thies . stated that he would review the

. implementation of the test. program.and determine.what c'ould.be done to

strengthen . the QA. program.#.a.this . area. . .thi said.that.without further

. . study, he would not be able to discuss specific steps that would be

taken.

I

e

.

_

_

_.

-

__

_

.

.

_.._

l

.

C0 Report No. 50-269/71-9

-7-

SECTION II

Prepared By:

C. E. Murphy

Reactor Inspector

ADDITIONAL SUBJECTS. INSPECTED,.NOT. IDENTIFIED IN SECTION I, WHERE NO

DEFICIENCIES OR UNRESOLVED ITEMS WERE FOUND.

None

DETAILS OF FUBJECTS DISCUSSED IN SECTION I

1.

Records Review

The insp'ectors reviewed the .following .0conee. records that contained

references to construction-related problems. The-purpose of the review

was .to determine if.the. record. identifying a problem also indicated

.the.resolutic of the problem. . Numerous . problems (See Exhibit A)

,

'

were identif

whose resolutions were not discussed in the records.

... ... .

Construction Records

Discrepancy Worksheets (Electrical)

October 30, 1970, to

October 4,1971

Discrepancy Worksheets (Instrumentation)

February 1970 to

June 1971

QC Random Inspection Worksheets

Number I-001 to I-237

Variation Notices (Instrumentation)

All

Electrical Cable Pull Sheets

Spot Check of Files

.

Daily Cogression Tesc Record-Form QC-6

May 1, 1970, to

October 9, 1971

Cadweld Splice Record - Form QC-10

All

Daily Record of Welding Defects - Form QC-22.

All

Daily Welcing Inspection - Form QC-17

October 1970 to

October 1971

l

l

i

<

. _ .

..._

_

_ . _ . _

.

.

.

. 3

' ~

00 Report No. 50-269/71-9

-8-

Hartford Insurance Reports

. . July 21,1971, to

September 24, 1971

Concrete Plant Logbook

Complete

Mechanical Inspector's Hanger Sketches

Spot Check

Civil Punch List

September 22, 1971, to

Present

Mechanical Punch List

Current List

Bechtel and Grinnell Hanger Surveillance

All

,

Sheets

"

Graph of Concrete Strength Breaks

All

Isometrics of Piping Systems

Spot Check

Cadweld Splice Summary - Form QC-13

All

Ultrasonic Inspection of Welds - Form QC-20

All

Compression Test Records - Form QC-3

November 28, 1969, to

October 12, 1971

Radiographic Inspection Report - Form QC-30

Spot Check

l

Operations Logs

Shif t Supervisor's Logs

June 22,1970, to

October 13, 1971

Duty Supervisor's Log

May 4, 1971, to

October 11, 1971-

Maintenance Log

January 5,1970,to

October 11, 1971

Electrical Log

June 12,1970, to

October 11, 1971

.

.

d

. . . . . -

-

-

.

CO Report No. 50-269/71-9

-9-

Babcock and Wilcox Field Service Log

. April 22, 1971, to

Augus t 28, 1971

Test Working Group Minutes

December 16, 1970, to

October 1971

Penetration Test Log

April 12, 1971, to

October 12, 1971

Instrument Work Group Kinutes

February 19, 1971, to

Oc tober 12, 1971

Control Room Logs

2.

Operations Work Orders

Upon completion of the review of the operating group's logs, the inspectors

discussed their. findings with Smith. . Smith agreed that .the logs did not

contain adequate documentation of .the . resolution of . problems. He stated

.that he was . planning .to . establish a work . order . system for use by his

people. A .special form with . serial . numbers .had been. ordered. Any

problem. identified by -a. member of.the operating.. group would be entered

on a work order. One copy would be given. co .the appropriate group for

correction of the problem. The original would be retained in a suspense

file until the problem was corrected. Upon completion, the forms would

be placed in the QA file. Smith stated that _the . system would be in

operation within thirty days. The inspector plans to follow up on this

item.

3.

Cable Tray Fill

During a DRL meeting at the site on September 16, 1971, the inspector

,

had observed that - cable trays that had been previously identified

as being overfilled 1/ appeared. to contain more cable than had been

previously observed. This was pointed. out to.P. .H.

Barton, Manager of

Nuclear and Technical Services for the licensee.and co A. Schwenaerof DRL.

The inspector commented that.the overfilled tray would appear not to

meet the requirements of Appendix A to 10 CFR 50. Schwencer concurred

and included this item in his . discussions with Barton. During this

inspection, the inspector requested a list of cables that had been

1,/ - C0 Report No. 50-269/71-5

.

'

.

00 Report No. 50-269/71-9

-10-

pulled in . trays which had.been.previously identified.as overfilled.

This list. contained approximately sixty. cables.that had been pulled

af ter Duke management had statedi .that no more cables would be installed

in these trays. After further discussions.with Aycock,.the inspector

was shown a copy of a. letter written by Beam.co C. .E.

Watkins, Vice

President, Construction, objecting.to .the. installation of cable in

.these trays. . .The inspector. discussed this . item.in. the management

interview and. stated.that.he would review .this - problem with Compliance

management. He . advised. Beam that.the. failure to take corrective action

appeared to be contrary to the requirements of Appendix B to 10 CFR 50.

4.

Inadequacies in QA Supervision

The . inspector asked Blaisdell.if work.had.been. completed on correcting

the deficiencies in the welding pro 9edures that_had.been previously

observed by. compliance. inspectors.2( Blaisdell. advised the. inspector

.that , '.because .of .other work, .very little. progress .had been made on

correcting the procedures. .The inspector. asked Blaisdell if he had

discussed the status of the. procedures with his supervision and he

. stated that.be. had not. The inspector then. questioned Blaisdell to

determine the . extent of the supervision .which he received.

In this

discussion, Jun indicated that his supervisor had.never discussed with

him his duties and. responsibilities, the duties .of.his unit, the

. procedures, . codes and regulations to be. observed in his work, the

status of his . work, or the . status of the . deficiencies. The inspector

.then questioned each of the. remaining field engineers concerning the

supervision which they had received. Each of the engineers answers

agreed totally with the answers given by Blaisdell. The inspector

. advised Beam that this appeared to be contrary to the requirements of

. Appendix B to.10 CFR 50 and would be discussed in the letter to the

licensee. This lack.of supervision was discussed in the management

interview.

(The inspector. received.a telecon.from Freeze on

'

October 19. 1971, in which Freeze stated.that a. system.of management

properly performing their functions.)2phat the QC. supervisors were

review was being instituted. to assure

The inspector also advised

1/ Letter from A. C. Thies, Senior.Vice President, Duke Power Company

to J. .G. Davis , CO:II, dated May 13, 1971.

2/ 00 Report 50-269/69-8; Letters from A. C. Thies, Senior Vice President

Duke Power Company, to J. ~ G. Davis, dated March 13, 1970 and June 18,

1971.

3/ Telecon from Duke (Freeze) to C0:II (Murphy) dated October 21, 1971.

I

,

1

_ _ _

. _ . _ . _ . _ _

-

- _ .. ._ _ _ . _

_ ..

_ __

.

_ ._

. . . _

.

..

.__.

'

es we # v

a

.

.

!

'

.

.

'

'~

CO Report No. 50-269/71-9

-11-

,

_

l

Beam .that the continued failure.to. take. action to correct- identified

.

welding procedure deficiencies. appeared to be contrary to the

i

requirements of Appendix B to 10 CFR 50.

I

1

i

i

i

h

,

4

'

I

i

t

f

a

&

'

f

,

!

!

!

.

4

1

-

!

!

i

I

a

!

<

[

!

.

4

1

4

t

e

i

f

l.

'

4

s

, - _ , -

5,- r .

.c

,.%.6-

,<-e

. _ _.

_,'my.

,

4 <-.

.

-,

, . . - . . . .

_ . - - ,

.,,,.....-.,e_

e v

-+,

..r

e

_ _ .

.

. - - _ .

-

. . .

.

-

,

)

CO Report No.

50-269/71-9

-12-

s

SECTION III

Prepared by:. W. . W. Peery

Radiation Specialist

Reviews were made. in a _ number.of _ specific . areas.of the . health physics

program. . Because of the incomplete status of. the. majority of these

items, no significant. inspection. itenc.were completed. The entire

subject. area will.be. reinspected.at.a.later time and these items

j

will be covered in a subsequent inspection.

4

. Attachments :

Exhibit A

.

1

'

.

e

_

_ _ . _ _ _ .

'

__

. . _ _ _

~

.

.

EXHIBIT A

' '

RESULTS OF RECORDS REVIEW

1.

Records that indicated the status or resolution of identified

problers .

Record Title

Dates or Serial Nos.

Inspector

Daily Compression Test Record

5/1/70 - 10/9/71

Swan

(Form QC-6)

Compression Test Record (Form QC-3) 11/28/69 - 10/12/7 L

Swan

Civil Punch List

All

Swan

Mechanical Punch List

All

Swan

Bechtel Hanger Surveillance Sheets All

Swan

Grinnell Hanger Surveillance

All

Swan

Sheets

Cadwald Splice Record

All

Swan

(Form QC-10)

Inspector's Isometrics Book (Welding) All

Swan

Daily Welding Inspection Record

10/70 - 10/71

Swan

(Form QC-17)

Radiographic Inspection Report

Spot Check

Swan

(Form QC-30)

Discrepancy Worksheets

10/70 - 10/71

Murphy

(Electrical)

Discrepancy Worksheets

2/70 - 6/71

Murphy

(Instrumentation)

Random Inspection Worksheets

I-001 to I-237

Murphy

(Form QC-53)

Cable Pull Sheets

Spot Check

Murphy

'

/

._ ._

- _ - _ .

M

s

'M

..

.

.

EXHIBIT A CONTINUED

Record Title

Dates or Serial Nos.

Inspector

Instrumentation States Logs

Sp'ot Check

Murphy

Control Room Logbook

Spot Check

Whitener

Maintenance Log

1/5/70 - 10/11/71

Cubitt

Electrician's Log

6/12/70 - 10/11/71

Cubitt

2.

Records that listed problems whose resolutions were not documented

with the entry.

,

Daily Record of Welding Defects All

Swan

a.

!

(Form QC-22)

Arc strike on transfer tube

9/17/71

Laminations in liner plate.

b.

Report of Hartford Steam

7/2/71 - 9/24/71

Swan

Boiler and Insurance . Company

Inspections.1/

The reports did not list the

resolution of any of the

identified problems.

c.

Test Working Group. Minutes

12/16/70 - 10/71

Whitener

Resolution of identified

probless not documented.

d.

Penetration Test Log

4/12/71 - 10/12/71

Whitener

Hydrostatic Test on

penetration no. 3 was

not successful.

(6/21/71)

e.

Instrument Working Group

2/19/71 - 10/12/71

Whitener

Meeting

Resolution of identified

problems not documented.

1/ These inspections are ensite audits made by Hartford people under

contract with Duke.

k

_

,

_

_

_.

__,

4

'

, s

>

,

e

's

EXHIBIT A CONTINUED

,

f.

Duty Supervisor's Log

5/4/71 - 10/11/71

Cubitt

Decay heat cooler deficiencies 10/11/71

(5/16/71)

,

g.

Shift Supervisor's Log

6/22/70 - 10/13/71

Cchitt

Resolution of identified

j

problems not documented

h.

B&W Field Service Log

4/22/71 - Present

Cubitt

Resolution of identified

problems not documented.

)

+

l

)

/

2

t,

s

'.-

'

.

1

i

i

!

.

Q '"

,

f

-

- . - - . .

I

,

w.

_

. -

,