Forwards IE Insp Repts 50-445/78-16 & 50-446/78-16 on 781002-31 & Notice of Violation
ML19322A182
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 11/17/1978
From: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Gary R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
Shared Package
ML19322A184 List:
References
NUDOCS 7901040224
Download: ML19322A182 (2)


See also: IR 05000445/1978016

Text

-

- - -

.

.

WM

1

g&

% ,o

E

4

UNITED STATES

NUCLEAR HEGULATORY COMMISSION

,,g_

_.

.o

REGION IV

- 5 . ..k

.j

G11 HYAN PLAZA DRIVE. SUITE 1000

c

ARLINGTON, TEXAS 7G011

.Q

f

.

% ', , , . #

November 17, 1978

i

In. Reply Refer To:

RIV.

Docket No. 50-445/Rpt. 78-16

50-446/Rpt. 78-16

Texas Utilities Generating Company

ATTN: Mr. R. J. Gary, Executive

President and General Manager

2001 Bryan Tower

Dallas, Texas

75201

Gentlemen:

This refers to the inspection activities perfonned by our Resident

Inspector, Mr. R. G. Taylor, during the period October 2-31, 1978,

of activities authorized by NRC Construction Permit Nos. CPPR-126

and 127 for the Comanche Peak facility, Units No.1 and 2, and to

the discussion of our findings with Mr. R. G. Tolson and other mem-

bers of your staff during the inspection period.

Areas examined during the inspection and our findings are discussed

in the enclosed inspection report. Within these areas, the inspection

consisted of selective ' examination of procedures and representative

records, interviews with personnel, and observations by the inspector-

During the inspection, it was found that certain activities under your

license appear to be in noncompliance with Appendix B to 10 CFR 50 of

the NRC Regulations, " Quality Assurance Criteria for Nuclear Power

Plants."

The Notice of Violation for the item of noncompliance reported in para-

graph 4 of the enclosed inspection report was forwarded to you by our

letter dated October 12, 1978; therefore, this letter does not require

further response regarding this matter.

During the inspection, it was found that certain of your activities

appeared to deviate from commitments in the FSAR. This item and ref-

erences to the specific commitments are identified in the enclosed

i

7901040AT?

  • -

.

,

Texas Utilitites Generating

Company

-2-

November 17, 1978

Notice of. Deviation. Please provide us within 30 days, in writing,

your comments concerning this item, a description of any steps that

have been or will be taken to correct it, a description of any steps

- that have been or will be taken to prevent recurrence, and the date

all corrective actions or preventive measures were or will be completed.

.

We have also examined actions you have taken with regard to previously

identified inspection findings. .The status of these items is identified

in paragraph 2 of the enclosed report.

0ne new unresolved item is identified in paragraph 6 of the enclosed

report.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If the report contains any information that you believe to be

proprietary, it is necessary that you submit a written application to

this office, within 20 days of the date of this letter, requesting that

such information be withheld from public disclosure.

The application

must include a full statement of the reasons why it is claimed that the

information is proprietary. The application should be prepared so that

any proprietary information identified is ' contained in an enclosure to

the application, since the application without the enclosure will also

be placed in the Public Document Room. .If we do not hear from you in

this regard within the specified period, the report will be placed in

-the Public Document Room.

Should you have any questions concerning this inspection, we will be

pleased to discuss them with you.

Sincerely,

[R

,;

c

W..C. SeOle, Chief.

Reactor Cdnstruction and

Engineering Support Branch

Enclosures:

1.

Appendix 'A, Notice of Deviation

2. . IE Inspection Report No. 50-445/78-16-

50-446/78-16

cc: w/ enclosures

L

LTexas Utilities Generating Company

ATTN:

Mr. H. C. Schmidt, Project Manager

2001. Bryan Tower

!

. Dallas, Texas

75201-