Forwards IE Insp Repts 50-456/80-04 & 50-457/80-04 on 800514-15 & Notice of Violation
ML19321A207
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 06/10/1980
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML19321A208 List:
References
NUDOCS 8007230002
Download: ML19321A207 (2)


See also: IR 05000456/1980004

Text

e2 "i

%,g

go

,

UNITED STATES

4

NUCLEAR REGULATORY COMMISSION

\\-

'

g

3 .,, ,

g

.

g

c

REGION ill

'

e

8

7M ROOSEVELT ROAD

E

o

GLEN ELLYN, ILLINOIS 6o137

.....

'JUN 1 0 W

Docket No. 50-456

Docket No. 50-457

Commonwealth Edison Company

ATTN:

Mr. Cordell Reed

Vice President

Post Office Box 767

' Chicago, IL 60690

Gentlemen:

This refers to the inspecLion conducted by Messrs. E. R. Schweibinz,

E. J. Gallagher and K. R. Naidu of this office on May 14-15, 1980, of

activities at the Braidwood Nuclear Power Station, Units 1 and 2, author-

ized by NRC Construction Permits No. CPPR-132 and No. CPPR-133 and to

the discussion of our findings with Mr. R. Cosaro and others of your

staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of

a selective examination of procedures and representative records, observ-

ations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in non-

compliance with NRC requirements, as described in the enclosed Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201 of

the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-

tions. Section 2.201 requires you to submit to this office within thirty

days of your receipt of this notice a written statement or explanation in

,

reply, including for each item of noncompliance:

(1) corrective action

taken and the results achieved; (2) corrective action to be taken to avoid

further noncompliance; and (3) the date when full compliance will be

achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter, the en-

closures, and your response to this letter will be placed in the NRC's

,

l

800723000%

Q

. . - . -

-

,

.

Commonwealth Edison Company

-2-

.

i

1

Public Document Room, except as follows.

If the enclosures contain in-

formation that you or your contractors believe to be proprietary, you

must apply in writing to this office, within twenty days of your receipt

of this letter, to withhold such information from public disclosure.

The application cust include a full statement of the reasons for which

the information is considered proprietary, and should be prepared so

that proprietary information identified in the application is contained

in an enclosure to the application.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

ha -k 0'$Nf" f

u

G. Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Report

No. 50-456/80-04 and

No. 50-457/80-04

cc w/ encl:

Mr. D. L. Peoples, Director

of Nuclear Licensing

Mr. R. Cosaro, Project

Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Mr. Dean Hansell, Office of

Assistant Attorney General

,

n

.