Tr.NNESSEE VALLEY AUTHORITY
/
cmTT ANOCG A. TENNESSEE 3]u,1 g pg,
400 Chestnut Street TowerT11tNTa. c u 5%
- 3 JUL 7 A9: 4l July 1, 1980 Mr. James P. O'Reilly, Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303
Dear Mr. O'Reilly:
0FFICE OF. INSPECTION AND ENFORCEMENT BULLETIN 79 RII:JPO 4
50-518, -519, -520, -521, -553, -554 - HARTSVILLE AND PHIPPS BEND NUCLEAR PLANTS Our initial response to your December 7, 1979, letter which transmitted OIE Bulletin 79-28, was submitted on February 6, 1980. The second interim report was submitted on March 28, 1980. Our investigations for the Hartsville and Phipps Bend Nuclear Plants have revealed that no NAMCO EA 180 limit switches are installed or planned for installation in any safety-related equipment, either inside or outside containment.
If you have any questions, please call Jim Domer at FTS 857-2014.
Very truly yours, TENNESSEE VALLEY AUTHORITY f'f
),
gir ~
L. M. Mills, Manager Nuclear Regulation and Safety cc: Office.of Inspection and Enforcement Division of Reactor Operations Inspection U.S. Nuclear Regulatory Commission Washington, DC 20555 GPP1CIAL COPY 8 0 0 7220.13 h An Laoat Opportumty Employe<
--