3
. *
,
.
.
.
.
.
.
.
'D
'
/
\\
)
UNITED STATES
%,/ .
NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
REGION IV
611 RYAN PLAZA DRIVE, SUITE 1000
ARLINGTON. TEXAS 76012
August 29, 1975
O
y
qw
w
-
I
we
w
-
k,
3-
Arkansas Power and Light Company
Docket No. 50-313
ATTN: .Mr. J. D. Phillips
. Senior Vice President
.
Sixth and Pine Streets
Pine Bluff, Arkansaa 71601
Gentlamen:
This refers to the-inspection conducted by Messrs D. C. Anderson and
~
R. Smith of this office on August 1S-21, 1975, of activities authorized
t,y NRC Oparating Licensa No. DPR-51 for the Arkansas Nuclear one, Unit 1
)
facility, and to the discucsion of our findings held uith Mr. J. U. Anderson
s
and other nenbars of your staff at the conclusion of the inspection.
,
Princips.1 areas c::acined during the inspection included:
(1) reactor
operations sinca the last increction; (2) action taken on Abnormal
occurrences; (3) record control; (4) procure:ent; (5) dosign, design
changes and modification; and (6) follou-up.on previousi identified
deviations and unrasolved items. Uithin these areau, the inspection
consisted of selective exasinations of ' procedures and reprasantative
'
,
records, intervicus with personnel, and observations by the inspectors.
-
During this inspection it was found that certain of your activities vere
not. conducted in full compliance with NRC requirements, ac set forth in
the Notice of Violation, enclosed horcuith as Enclosure (1). This
notice is sent to you pursuant to the provisions
e,. Sect!on 2.201 of the
NRC's " Rules of Practice", Part 2, Title 10, Code of Federal Regulations.
-
Section 2.201~ requires you to submit to this office, uithin 20 days of
, your roccipt of this notice, a written statem2nt or explanation in reply
including:
(1) corrective steps which have been taken by you, and the
results achieved;'(2) correctiva steps which will be taken to cvoid
further noncomplicace; and (3) the date when full complinnce will be
,
achieved.
-
,Do)
I
8004140 79
..
,.
<
--
, ,
,
n
.,
n
-
--.,.
,
.
.
,
'
,
,
.
.
s
( v /.
.
Arkansas Power & Light Company
-2-
0
In accordance uith Section 2.790 oi tN NRD's " Rules of Picctice",
Part 2, Title 10, Code of Federal Regulations, a copy of this letter
and the enclosed inspection report will be placed in the NRC's Public
Document Room. If this report contains any information that you or
<
your concractors believe to be proprietary, it is necessary that you
,
naka a written applicacien within 20 days to this office to vi:hhold
i
such information from public disclosure. Any such application must
include a full statement of the reasons on the basis of which it is
claimed that the information is proprietary, and should be prepared so
that proprietary information identified in the application is contained
in a separate part of the document. If we do not hear from you in this
regard within the specified period, the report will be placed in the
,
Public Docunent Room.
Should you have any questions concerning this inspection, we vill be
-pleased to discuss them with you.
Sincerely,
i
V
-
f b Wj'.;5
G. L. Madsen, Chief,
Reactor Construction and
Operations Branch
.
Enclosures
~
1.
Appendix A - Notice of Violation
2.
IE Inspection Report No. 50-313/75-09
'
.