_m 7
k,e.,eb.
~
Flor'ida Y
March 23, 1973
~
' -l 3
Mr. Norman..Moseley,/ Director
~
'U.5. Atomic ~ Energy Comission'-
~
Directo' rate' of Regulatory Ope' rations Region II, Suite 818 230 Peachtree Street N.W.
Atlanta, Georgia 30303
Subject:
Crystal River Unit #3 Refer: R0: II: EJV 50-302/73-1
Dear Mr. Moseley:
. In.r'espon' e. to Mr. J. G.. Davis. letter.o# March 2,1973, cdncerning. the -
~
s
~
' inspection' of%ur Crystal River Unit #?. facility conducted by your ~
.Mi.~.Herdt on January 23-25, 1973, we submit the following. reply to the indica,ted appaieni;.non.complian;ss with Appendix B..to 10 CFR50.
'Wtth respect' to. Item ho. '73-1/Al Decdy. Heat and Makeup and Purification.
Systems '.'elding, the following acti,on was taken:
1.
A review of 730 completed Field Weld Data Sheets was made.
Results of the review show that nineteen (19) welds were completed to Procedure SS-1-Tig using the wrong rod size for part of the weld. These nineteen welds will be 100%
radiography inspected to provide evidence that the welds are acceptable.
2.
Welding procedure SS-1-Tig has since been revised to allow the use of 3/32" filler metal for the first pass.
3.
FPC Work Procedure No. W-21 has also been revisec' to require the applicable welding procedure number to be stated on l-the Welding Rod Withdrawal Order.
Only rod sizes called for by the procedure will be issued to the welder.
4.
The welding inspectors have been instructed to check to see that weld rod size in use is in accordance with the procedure, in addition to other inspection checks.
. 8 0 0s.0 4 o bW
+-
V Mr. Norman Moseley March 23,1973 5.
Piping supervision issued instructions to the foremen in charge of welding, stressing the importance of strict adherence to welding procedures, including proper rod size.
6.
Quality control has added a Q.C. ' Inspector whose primary duty is to, perform in-p,rocess inspections of welding operations.
WitN respe' t to Item' No. 73'-1/A2. Decay Heat and Makeup and P'urification c
,., Systems Radiographs, the;following: action was..ta, ken:
~
l c.. ' Ins.tructed the radiogpaphers 'to.Reep the genetra' meter located ine
~.accordance. wi th..th5 : pr'ocedure.
/
., e
~
~ :.<
"2. ', Recalled all film fdr. review of' penetramet,er locati.o_n; 4
- 3.,PresenN1y comp'ii'ing 'a 1,ist'of all fil'm that does ndt meet
' ~
penetrameter location requirement.
Documents concerning the above will be maintained at the site for review by your inspectors during their next visit.
Please advise if further response is required.
... Ve'ry truly y. urs,
o
.. ; j,
.,r
.'l J. I. Rodge.rs.
~'
Asst..Vi ce. President i.-
~ ~ JTR/iw'. -
N e
e