ML19318C728
| ML19318C728 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 05/08/1980 |
| From: | Robert Carlson NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Dunn C DUQUESNE LIGHT CO. |
| Shared Package | |
| ML19318C729 | List: |
| References | |
| NUDOCS 8007020216 | |
| Download: ML19318C728 (2) | |
See also: IR 05000334/1980010
Text
- - - - _ _ _ _ _ - - _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _
Y%
-
UNITED STATES
[ ,,,, jo
NUCLEAR REGULATORY COMMisslON
[
o
REGION I
!!
$
$31 PARK AVENUE
f
KING OF PRUSSIA PENNSYLVANIA 19406
\\*****/
MAY 0659
Docket No. 50-334
Duquesne Light Company
ATTN: Mr. C. N. Dunn
Vice President
Operations Division
435 Sixth Avenue
Pittsburgh, Pennsylvania 15219
Gentlemen:
Subject:
Investigation Report No. 50-334/80-10
This refers to the investigation conducted by Mr. J. P. Durr of this
office on April 8-9, 1980 at Beaver Valley Power Station, Unit No.1,
Shippingport, Pennsylvania of activities authorized by NRC License No. DPR-
66 and to the discussions of our findings held by Mr. Durr with Mr. H.
Williams of your staff at the conclusion of the investigation.
Areas examined during this investigation are described in the Office of
Inspection and Enforcement Investigation Report which is enclosed with this
letter. Within these areas, the inspection consisted of selective examinations
of procedures and representative records, interviews with personnel, and
observations by the inspector.
Within the scope of this investigation, no iteins of noncompliance were
observed.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
investigation report will be placed in the NRC's Public Document Room.
If
this report contains any information that you (or your contractor) believe
to be proprietary, it is necessary that you make a written application
within 7.0 days to this office to withhold such information from public
disclosu,a. Any such application must be accompanied by an affidavit
executed by the owner of the information, which identifies the document or
part sought to be withheld, and which contains a statement of reasons which
addresses with specificity the items which will be considered by the Commission
as listed in subparagraph (b) (4) of Section 2.790.
The information sought
to be withheld shall be incorporated as far as possible into a separate
part of the affidavit.
If we do not hear from you in this regard within
the specified period, the report will be placed in the Public Document
Room.
,
80070200/[o
j
j
._ - ______
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
..
.
Duquesne Light Company
2
No reply to this letter is required; however, should you have any questions
concerning this investigation, we will be pleased to discuss them with
you.
Sincerely,
n
Robert T. Carlson, Chief
.
Reactor Construction and Engineering
'
Support Branch
Enclosure: Office of Inspection and Enforcement Investigation
Report Number 50-334/80-10
cc w/ enc 1:
F. Bissert, Technical Assistant Nuclear
R. Washabaugh, QA Manager
J. Werling, Station Superintendent
G. Moore, General Superintendent, Power Stations Department
J. J. Carey, Director of Nuclear Operations
R. Martin, Ituclear Engineer
J. Sieber, Seperintendent of Licensing and Compliance, BVPS
,
.
.
-