[$C-
/paadoso,
NUCLEAR REGULATORY COMMISSION
UNITED STATES
'-
O S . M'/ j
R EGloN IV
E I)
I o
611 RY AN PLAZA DRIVE, SUITE 1000
G p~ i ,'_
.
.-
ARLINGTON, TEXAS 76012
s .~. . .f,.f
%
'
-
April 30, 1980
i
.
In Reply Refer To:
RIV
Docket No. 50-445/Rpt. 20-12
50-446/Rpt. 80-12
j
Texas Utilities Generating Company
ATTN:
Mr. R. J. Gary, Executive Vice
President and General Manager
'2001 Bryan Tower
'
Dallas,' Texas 75201
Gentlemen:
This refers to the meeting held by Messrs. K. V. Seyfrit, W. C. Seidle,
W. E. Vetter, W. A. Crossman and R. G. Taylor with you and other members of
your staff on April 8,1980, at the Region IV ofiirca in Arlington, Texas,
in regard to reporting of significant construction deficiencies.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If the
report contains any information that you believe to be proprietary, it is
necessary that you submit a written application to this office, within 20 days
of the date of this letter, requesting that such information be withheld from
public disclosure. The application must include a full statement of the reasons
why it is claimed that the information is proprietary. The application should
be prepared so that any proprietary information identified is contained in an
enclosure to the application, since the application without the enclosure will
also be placed in the Public Document Room.
If we do not hear from you in this
regard within the specified period, the report will be placed in the Public
Document Room.
Should you have any questions concerning this inspection, we will be pleased
to discuss them with you.
Sincerely,
.
%
W.C.Seikle, Chief
i
Reactor Construction and
Engineering Support Branch
8 0 0 619 0Q/6
_
.
_
.
._ . __
.
Texas Utilities Generating
Company
-2-
April 30, 1980
Enclosure:
IE Inspection Report No. 50-445/80-12
50-446/80-12
cc: w/ enclosure
Texas Utilities Generating Company
ATTN:
Mr. H. C. Schmidt, Project Manager
2001 Bryan Tower
Dallas, Texas-
75201
.,
J
4
f
a
,_.
,.
. , . _ - -
.
._
. . _ , , _
.y,,
.,