Responds to NRC Re Violations Noted in IE Insp Rept 50-346/75-16.Corrective Actions:B&W Field Const Procedure Deviation 153-01 Developed to Document Repair Procedure Starting from Inner Wall
ML19317F581
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/09/1975
From: Roe L
TOLEDO EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19317F576 List:
References
NUDOCS 8001150902
Download: ML19317F581 (2)


Text

O

~

fx TOLEDO

(

)

% Ei[)lEiC)rd V

LOWELL E. ROE

v.. pr.......

...a.... o

...~a s (4198 259-5242 October 9, 1975 Decket No. 50-346 Mr. James G. Keppler Regional Director, Region III Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Keppler:

Toledo Edison acknowledges receipt of your September 16, 1975 letter and enclosure referencing an apparent noncompliance with NRC regulations.

g'w\\

This item resulted from the site inspection conducted by your office on t

j August 18-20, 1975.

V Toledo Edison offers the following information regarding the apparent noncompliance, including corrective action and steps taken to avoid further occurrences.

Item A-2:

Contrary to 10CFR50, Appendix B, Criterion V, Repairs to Reactor Coolant Pump 1B1 were being performed without an approved Procedure.

(Report Details, Paragraph 1)

The repair work that was being done involved removal of an indication in the pump casing found as a result of the In-Service Baseline Inspection radiography.

The calculated location of the indication in the casing was such that the most logical approach to repairs was to start removal of material from the outer side of the casing wall. The repair procedure was developed to remove the indication and repair work commenced.

The indi-cation was not found at the depth calculated and further evaluation showed that the indication location could be better reached by starting from the inner wall.

This work was commenced, using the same procedure, and work was in progress at the time of the NRC inspection.

Work was stopped immediately by the B&W Quality Control Supervisor and B&W Field Construction Procedure Deviation 153-01 was developed to precisely document that the repair procedure was applicable to repair work starting

[l from the inner wall. This procedure deviation was approved by Bechtel

()

Construction Management on August 21, 1975.

Following this approval, work was resumed on the Reactor Coolant Puup 1B1 Casing Repairs.

THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MAOISON AVENUE TOLEOO. CHIO 43652 8001150 @ @

I

}

Mr. James G. Keppler

}

Docket No. 50-346 October 9, 1975 1

f Page 2 i

l

\\

In the future, both B&W and Bechtel will exercise more care in the development, approval and use of B&W Field Construction Procedures so that the procedures fully apply to the work being performed.

i 1

Yours truly, 1

i Lowell E. Roe l

Vice President Facilities Development LER/mkn i