UN1 Oconta Unit 3 q
U DATE 10/10/77 DOCKET NO. 50-2o7 PREPARED BY J.
A.
Reavis OPERATING STATUS 1.
REPORTING PERIOD: September 1 THROUGH September 30, 1977 GROSS HOURS IN REPORTING PERIOD:
720.00 2.
CURRENTLY AUTHORIZED POWER LEVEL (MWt): 2568 NET CAPABILITY (HWe-Net):
860 3.
POWER LEVEL TO WHICH RESTRICTED (IF ANY):(MWe-Net) 4.
REASONS FOR RESTRICTION (IF ANY)
This Month Year to Date Cumulative 5.
NUMBER OF HOURS THE REACTOR WAS CRITICAL 720.00 5630.82 19033.52 6.
REACTOR RESERVE SHUTDOWN HOURS 7.
HOURS GENERATOR ON-LINE 712.71 5548.55 18572.05 8.
UNIT RESERVE SHUTDOWN HOURS 9.
GROSS THERMAL ENERGY GENERATED (MWH) 1743415 13739161 44107378 10.
GROSS ELECTRICAL ENERGY GENERATED (gg) 603630 4771470 15210914 11.
NET ELECTRICAL ENERGY GENERATED (mm) 574837 4549109 14482751 12.
REACTOR SERVICE FACTOR 100.00 85.95 77.75 13.
REACTOR AVAILABILITY FACTOR 98.99 84.78 77.89 14.
UNIT SERVICE FACTOR 98.99 84.70 75.87 15.
UNIT AVILABILITY FACTOR 98.99 84.70 75.87 16.
UNIT CAPACITY FACTOR (Using Net 92.84 80.75 68.80 Capability) 17.
UNIT CAPACITY FACTOR (Using Design Mwei 90.01 78.29 66.70 18.
UNIT FORCED OUTAGE RATE 1.01 15.30 14.37 19.
SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE & DURATION OF EACH:)
Refueling - October 22, 1977 - 6 weeks 20.
IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
REACTOR SERVICE FACTOR = HOURS REACTOR WAS CRTTICAL X 100 HOURS IN REPORTING PERIOD REACTOR AVAILABILIU FACTOR = HOURS REACTOR WAS AVAILAliLE TO OPE 1 ATE X 100 Il0URS IN REPORTING PERIOD UNIT SERVICE TACT 0n
= HOPPS CD:ERATOR ON LINE 7912170 k HOURS IN REPORTING PERIOD UNIT AVAILABILITY FACTOR = 1100RS UNTT WAS AVATIABLE 20 GENERATE X 100 HOURS IN REPORTING PERIOD UNIT CAPACITY FACTOR
= NET ELECTRICAL P0hER CDiERATED
[N it Capability or Design (MW-Net)]. X !!OURS IN REPOKTfNb PERIOD UNIT FORCED OUTACE RATE e FORCFD OUTAGE HOURS X 100 HOURS GENEPaTOR ON LINE + FORCED OUTAGE HOURS
DOCKET NO. 50-287 UNIT oconee Unit 3 10/10/77 DATE AVERAGE DAILY UNIT POWER LEVEL MONTH september, 1977 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-net)
DAY (MWe-net) 1 850 17 842 539 2
18 839 839 3
19 681 837 4
836 5
21 853 839 6
22 853 839 7
23 723 838 8
24 838 9
25 S37 10 810 26 11 27 838
)
850 835 12 28 845 13 29 835 830 14 30 847 15 844 DAILY UNrr POWER LEVEL FORM INSTRUCTIONS On this form, list the average daily unit power level in MWe-net for each day in the reporting month.
I Compute to the nearest whole megawatt.
These figures will be used to plot a graph for each reporting month. Nate that by using maximum dependable capacity for the net electrical ratmg of the unit. there may be iicasions when the daily average power level exceeds the 100'1 line (or the restricted power lesel hne). In such c.nes, the average daily unit power output sheet should be footnoted to explain the cpparent anomaly.
DdCKET NO. 50-287 UNIT SHUTDOWNS UNIT NAMii Oconee Unit 31 10/10/77 DATli REPORT MONTil _ September, 1977 TYPE METHOD OF F-FORCED DURATION SHUTTING DOWN NO.
DATE S SCHEDULED (HOURS)
REASON (1)
THE REACTOR (2)
CORRECTIVE ACTIONS / COMMENTS 10 77-09-2 F
7.29 D
1 Reactor Building spray pump out of service more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
Shutdown per Oconee Technical Specifica-cation 3.3.
(1) REASON (2) ME1110D A -EQUIPMENT F ALLURE (EXPLAIN) 1-MANUAL B - M AINT. OR TEST.
2-MANUAL C. RIJUELING
~
SCRAM D-REGULATORY RESTRICTION 3-AUTOM ATIC E-OPERATOR TRAINING AND SCRAM LICENSE EXAMINATION 4-Other F-ADMINIST R ATIVE G-OPLRATIONAL FRROR IEXPLAIN)
Il-OillER IEXPLAIN)
SUMMARY
No major outage this month.