UNI'.
, con u Unit 1 DATE 10/10/77 DOCKET NO. 50-269 PREPARED BY J. A.
Reavis OPERATING STATUS 1.
REPORTING PERIOD: September 1 THROUGH September 30, 1977 GROSS HOURS IN REPORTING PERIOD:
720.00 2.
CURRENTLY AUTHORIZED POWER LEVEL (MWt): 2568 NET CAPABILITY (MWe-Net):
860 3.
POWER LEVEL TO WHICH RESTRICTED (IF ANY):(MWe-Net) 4.
REASONS FOR RESTRICTION (IF ANY)
This Month Year to Date Cumulative 5.
NUMBER OF HOURS THE REACTOR WAS CRITICAL 0
3835.41 25951.21 6.
REACTOR RESERVE SHUTDOWN HOURS 7.
HOURS GENERATOR ON-LINE O
3777.64 23741.63 8.
UNIT RESERVE SHUTDOWN HOURS 9.
GROSS THERMAL ENERGY GENERATED (MWH) 0 8879906 55265617 10.
GROSS ELECTRICAL ENERGY GENERATED (MWH) 0 3065630 19189060 11.
NET ELECTRICAL ENERGY GENERATED (MWH)
(4695) 2897471 18130004 12.
REACTOR SERVICE FACTOR 0
58.55 70.31 13.
REACTOR AVAILABILITY FACTOR 0
59.66 66.72 14.
UNIT SERVICE FACTOR 0
57.67 64.32 15.
UNIT AVILABILITY FACTOR 0
57.67 64.40 16.
UNIT CAPACITY FACTOR (Using Net 0
51.43 57.11 Capability) 17.
UNIT CAPACITY FACTOR (Using Design Mwe) 0 49.86 55.37 18.
UNIT FORCED OUTAGE RATE O
27.31 19.41 19.
SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE & DURATION OF EACH:)
20.
IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
October 16, 1977 REACTOR SERVICE FACTOR = HOURS REACTOR WAS CRTTICA1. X 100 HOURS IN REPORTING PERIOD RZACTOR AVAILABILI'lY FACTOR = Hot 1RS REACTOR UAS AVAIIAEl.E TO OPERATE X 100 110URS IN REPORTING PERIOD UNIT SERVICE FACTOR
= HOPPS CD:ERATOR ON I.1NE HOURS IN REPORTING PERIOD UNIT AVAILABILITY FACTOR = 110URS ttNTT_ WAS AVA11ABI.E TO GENERATE X 100 HOURS IN REP 0kTING PERIOD
= NET ELECTRICAL POWER CENERATED.7 91 UNIT CAPACITY FACTOR (Not Capability or Design (Mwe-Net)] X 110VRS IN nl:PORTTL. 9 PERIOD UNIT FORCED OUTACE RATE - FORCED OUTAGE 1K%RS i
HOURS GENERATOR ON 1.INE + FORCED CUTAGE HOURS
DOCKET NO.50-269 0conee Unit 1 W IT DATE AVERAGE DAILY UNIT POWER LEVEL MONTH Sentember. 1977 AVERAGF DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-net)
DAY (MWe-net) 1 17 2
18 3
19 4
20 5
21 6
22 7
23 8
24 9
25 10 26 11 27 12 28 13 29 14 30 15 31 16 DAILY l' NIT POWER LEVEL FORM INSTRUCTIONS On thE form, list the average daily unit power level in MWe-net for each day m the reporting month.
Compute to the nearest whole megawatt.
These figures will be used to plot a graph for each reporting month. Note that by using maximum dependable capacity for the net electrical ratmg of the unit. there may be.it casions when the daily average power level exceeds the 10074 line tor the restricted power lesel hne). In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.
l l
D CKE F NO. 50-269 Oconee Unit 1 UNIT SHUTDOWNS UNIT NAMii 10/10/77 DA'TE RiiPORT MONTil September, 1977 TYPE METHOD OF F-FORCED DURATION SHUTTING DOWN NO.
DATE S SCHEDULED (HOURS)
REASON (1)
THE REACTOR (2)
CORRECTIVE ACTIONS /CCMMENTS 14 77-09-01 S
408.00 C
1 Refueling 15 77-09-10 S
312.00 B
N/A Steam generator maintenance (1) REASON (2) METilOD A -EQUIPMENT F AILURE (EXPLAIN) l-MANUAL B - MAINT. OR TEST.
2 - M ANUAL C-REI UELING SCR AM D-REGULATORY RESTRICTION 3-AUTOM ATIC E-OPER ATOR TRAINING AND SCR AM LICENSE EXAMINATION 4-Other F-ADMINIST R AllVE G-OPERATIONAL ERROR IEXPLAIN)
II-OlllLR IEXPLAIN)
SUMMARY
Refueling completed.
Outage extended for inspection of steam generator.
-