Requests Extension of Completion Date from 720630 to 730228 for Provisional CPPR-33
ML19317D955
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 06/02/1972
From: Thies A
DUKE POWER CO.
To: Anthony Giambusso
US ATOMIC ENERGY COMMISSION (AEC)
Shared Package
ML19317D952 List:
References
NUDOCS 7912100633
Download: ML19317D955 (2)


Text

-

Duxu Powzn COMPANY Powra Buit.orso 4ca SouTn Cuuncu Srazer, Cu Ant.oTTE,N. C. como.

A. C. M cs P. o. Box 2:7e semon VsCg Passiognt Paoovetio= a o ina.mssion June 2, 1972 c3 g) / s\\

t.

/

/

On,

5' S'.

/ /,",I Mr. Angelo Gia=busso Deputy Director for Reactor Projects 5t,

(a o

W, {'jj Directorate of Licensing

]

c?.'.,

D '... 7 0.O-d '

A A

United States Atomic Energy Cor=ission Washington, D. C.

20545 v,.

A U

Re: Oconce Nuclear Station f

i g cp D

Unit 1 Docket No. 50-259 Provisional Construction Permit No. CPPR-33 Application for Renewal of Construction Permit r

Dear Mr. Giambusso:

We hereby apply for an extension of time for the completion of Oconee Nu-clear Station Unit 1 as covered by Provisional Construction Permit No.

CPPR-33.

The original construction permit called for completion of the facility by Febre.ary 28, 1971..

This date was extended to September 30,1971 by your order dated February 27, 1971, to January 31, 1972 by your order dated August 27, 1971, and to June 30, 1972 by your order dated January l

28, 1972. As mentioned in our letters of February 19, August 6, and t

' December 20, 1971, delays produced by le.te delivery of major reactor coolant components, the replaccment of reactor coolant pumps, and excessive vibration of the reactor coolant pu=ps have extended the original schedule considerably.

In addition to these delays, damage to the steam generators and to the reactor vessel internals by loose parts which was reported to you by my letter of April 4, 1972 has again extended the anticipated construction completion date. We now expect that the facility will be 3.for fuel loading about January'15,1973.

read We hereby request that the latest completion date specified in Construction

?ermit No. CPPR-33 be extended from June 30, 1972 to May 1, 1973 to provide a suitable margin.

Very truly yours, c:;f

A.'C.' Thies 12100$ D ACT:vr,

.s.,

NORTH CAROLINA A

)

)

MECKLENBURG COUNTY )

A. C. THIES, being duly sworn, states that h President of Duke Power Company; that h e is Senior Vice said Company to sign and file with the Ate is authorized on th Application for Renewal of Constructio omic Energy Commission this n Permit; the statements contained in such A that he has read all of made and m$tters set forth therein are trupplication; and t knowledge,'information and belief e and correct to the best of his r

kJ d$$6" A*. D. Thies

~

Subscribed and sworn to before me the State and County above named

, a Notary Public in and for this 2nd day of June, 1972.

(<y%'2 h

, n, :. t.'._

s 5otary Public

% x.yD J

//

/

/

./

My Commission Expires:

./

j'/OA:rtl, /!.!'}f.?

e e

p 4

$