Forwards IE Insp Repts 50-445/80-09 & 50-446/80-09 on 800312-14 & Notice of Violation
ML19312E527
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 04/07/1980
From: Brown G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Gary R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
Shared Package
ML19312E525 List:
References
NUDOCS 8006050115
Download: ML19312E527 (2)


See also: IR 05000445/1980009

Text

_

e

.

,

  • Ho ,,fo

u

UNITED STATES

NUCLEAR REGULATORY COMMISSION

-

7

g

  • '*.

REGloN IV

o

7

i) ^

o

611 RY AN PLAZA DRIVE, SUITE 1000

7. jg [

. .j

ARLINGTON, TEXAS 76012

g

o

g

\\; +' .w. '. . /

0 7 APR 1980

In Reply Refer To:

RIV

Docket Nos. 50-445/Rpt.

80-09

50-446/Rpt.

80-09

Texas Utilities Generating Company

ATTN: Mr. R. J. Gary, Executive Vice

President and General Manager

2001 Bryan Tower

Dallas, Texas

75201

Gentlemen:

This refers to the inspection conducted by Mr. Lorenzo Wilborn during the

period March 12-14, 1980, of activities authorized by NF.C Construction Permit

Nos. CPPR-126 and 127 for the Comanche Peak Project Units No. 1 and 2, and to

the discussion of our findings with Mr. J. T. Merritt and other members of

your staff at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted

of selective examination of procedures and representative records, interviews

with personnel, and observations by the inspector.

Based on the results of this inspection, it appears that one of your activities

was not conducted in full compliance with NRC requirements as set forth in the

Notice of Violation, enclosed herewith as Enclosure 1.

This notice is sent to you pursuant to the provisions of Section 2.201 of the

NRC " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office, within thirty (30) days

of your receipt of this notice, a written statement or explanation in reply

including (1) corrective actions which have been taken by you and the results

achieved; (2) corrective actions which will be taken to avoid further items of

noncompliance; and (3) the date when full compliance will be achieved.

One new unresolved item is identified in paragraph 5.a. of the enclosed report.

-. * * * *?5 9 g\\G

.

.

_

'

.

Tuan Utilities Gensrating Comp ny

2

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If the

report contains any information that you believe to be proprietary, it is

necessary that you submit a written application to this office, within 20 days

of the date of this letter, requesting that such information be withheld from

public disclosure. The application muse. include a full statement of the reasons

why it is claimed that the information c proprietary.

The application should

be prepared so that any proprietary it ' - mation identified is contained in an

enclosure to the application, since tim application without the enclosure will

also be placed in the Public Document Room.

If we do not hear from you in this

regard within the specified period, the report will be placed in the Public

Document Room.

Should you have any questions concerning this inspection, we will be pleased

to discuss them with you.

Sincerely,

J-

?&E

G. D. Brown, Chief

Fuel Facility and Material

Safety Branch