Forwards Corrected Page 2 to IE Bulletin 78-01, Flammable Contact-Arm Retainers in GE CR120A Relays
ML19312C325
Person / Time
Site: Oconee, Mcguire, McGuire  Duke Energy icon.png
Issue date: 02/13/1978
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parker W
DUKE POWER CO.
References
IEB-78-01, IEB-78-1, NUDOCS 7912130855
Download: ML19312C325 (3)


Text

e

  1. jA2as;eq' UNITED STATES j~- g j[

c,,

NUCLEAR REGULATORY COMMISSION

/ ;

M /. -- '

[,3y g

R EGION II

'M;y

.. a 230 PEAcHTREE STREET, N.W. SUITE 818 g

o

' i!

x ATLANTA, GEORGI A 30303 C '[

InRep[y*YeferTo:

FEB 131978

~

RII:JPO 50-369, 50-370 50-269, 50-270 50-287 Duke Power Company Attn:

Mr. William O. Parker, Jr.

Vice President, Steam Production P. O. Box 2178 422 South Church Street Charlotte, North Carolina 28242 Gentlemen:

The copy of IE Bulletin No. 78-01 which was sent to you contained an error on page 2.

Would you please destroy that page and substitute the enclosed corrected page.

Sincerely, 4

James P. O'Reilly Director

Enclosure:

As Stated 1

cc w/ encl:

J. C. Rogers, Project Manager McGuire Nuclear Station P. O. Box 2178 Charlotte, North Carolina 28242

7912130 v

VV

FEB 131978 Duke Power Company

_2 (ce's cortinued)

M. D. McIn;osh, Plant Manager McGuire Nuclear Station P. O. Box 488 Cornelius, No*:th Carolina 28031 J. E. Smith, Station Manager Oconee Nuclear Station P. O. Box 1175 Seneca, South Carolina 29678 l

l i

.. -. L. -...

CORRECTED COPY IE Bulletin No. 78-01 January 16, 1978 1

2.

Identify all of the relays that have Celcon contact-arm retainers.

3.

For those relays which have Celcon recainers, develop a program for their replacement with Velox retainers. The program should include:

Identification of the location of the relays a.

b.

The schedule for the replacement of the Celcon retainers The procedure that will be used to perform the replacement, c.

including the means that you will use to di#ferentiate between the Valox and Celcon retainers.

4.

For facilities with an operating license, a report of the above actions, including the date(s) when they will be completed, shall be submitted within 30 days of receipt of this Bulletin.

5.

For facilities with a construction permit, a report of the above actions, including the date(s) when they will be completed, shall be submitted within 60 days of receipt of this Bulletin.

Reports should be submitted to the Director of the appropriate NRC Regional Office. A copy of your report should be sent to the U.S.

Nuclear Regulatory Commission, Office of Inspection and Enforcement, Division of Reactor Operations Inspection, Washington, D.C.

20555.

Approved by GAO, B-180225 (R0072); clearance expires 7-31-80.

Approval was given under a blanket clearance specifically for identified generic problems.

Attachment:

Copy of Text of General Electric Service Instruction Letter (SIL)-SIL-No. 229 2 of 2 CORRECTED COPY

,