ML19309H402
| ML19309H402 | |
| Person / Time | |
|---|---|
| Site: | 07001100 |
| Issue date: | 04/03/1980 |
| From: | Lichtenberger H ABB COMBUSTION ENGINEERING NUCLEAR FUEL (FORMERLY |
| To: | Martin W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| Shared Package | |
| ML19309H400 | List: |
| References | |
| NUDOCS 8005130154 | |
| Download: ML19309H402 (1) | |
Text
-_
C-E Power Systems Tel 203/688-1911 O
8005130I Combustion Engineenng, Inc.
Telex: 99297 2
1000 Prospect Hill Road Windsor. Connecticut 06095 H SYSTEMS POWER April 3,1980 License SNM-1067 Docket 70-1100 U. S. Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, PA 19406 Attention: Mr. Walter G. Martin, Chief Safeguards Branch
Reference:
Letter from Mr. Walter G. Martin to Mr. H. V. Lichtenberger, dated March 26, 1980; Inspection 70-1100/80-01 Gentlemen:
This is in response to the above referenced letter in which you reported one item of noncompliance which was determined during your inspector's visit to our facility on February 12, 13, 26-28, 1980.
Appendix A The material unaccounted for (MUF) was not calculated for the December 13, 1979 low enriched uranium physical inventory within 30 dayr of the start of the physi-cal inventory as required.
Response
On February 1,1980 we informed Region I that the physical inventory which was taken on December 13, 1979 could not be reconciled because of a number of data processing problems. We also stated that we planned to perform a reinventory.
An immediate action letter (IAL 80-02) dated February 4, 1980 was sent to us by your office which required the following actions:
1)
Immediately begin preparations for a complete reinventory of special nuclear material.
?)
Initiate this reinventory no later than February 22, 1980.
3)
Provide the results of this reinventory to Region I within 30 days after the start of the inventory.
All of the above actions have been completed satisfactorily, our data processing problems have been resolved, and we are in full compliance at this time.
Very trul yours, H. V.
ichten erger Vice President-Nuclear Fuel Nuclear Power Systems-Manufacturing HVL/GJB/ssb