Forwards IE Insp Rept 50-213/79-21 on 791217-20 & Notice of Violation
ML19309F906
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 02/25/1980
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Counsil W
CONNECTICUT YANKEE ATOMIC POWER CO.
Shared Package
ML19309F902 List:
References
NUDOCS 8005010615
Download: ML19309F906 (2)


See also: IR 05000213/1979021

Text

615

-

-

8005 010

,

UNITED STATES

]o

NUCLEAR REGULATORY COMMI .slON

y

o

REGION I

$

j

631 PARK AVENUE

$s,p

/g

KING OF PRU551 A, PENNSYLVANIA 19406

FEB 2 5 1980

Docket No. 50-213

Connecticut Yankee Atomic Power Company

ATTN: Mr. W. G. Counsil

Vice President - Nuclear

Engineering and Operations

P. O. Box 270

Hartford, Connecticut 06101

Gentlemen:

Subject:

Inspection 50-213/79-21

This refers to the inspection conducted by Mr. J. T. Shedlosky of this office on

December 17-20, 1979 at the Haddam Neck Plant, Haddam, Connecticut of activities

authorized by NRC License No. DPR-61 and to the discussions of our findings held

by Mr. D. F. Johnson with Mr. R. Graves and other members of your staff at the-

conclusion of the inspection, and to a subsequent telephone discussion between

Mr. W. G. Counsil and Mr. J. M. Allan on December 21, 1979.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, measurements made by the

inspector, and observations by the inspector.

Based on the results of this inspection, it appears that one of' your activities

was not conducted in full compliance with NRC requirements, as set forth in the

Notice of Violation, enclosed herewith as Appendix A.

This item of noncompliance

has been categorized into the levels as described in our correspondence to you

c

l

dated December 31, 1974.

This notice is sent to you pursuant to the provisions

of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Ccde of

)

Federal Regulations. Section 2.201 requires you to submit to this office,

j

within twenty (20) days of your receipt of this notice, a written statement or

'

explanation in reply including:

(1) corrective steps which have been taken by

you and the results achieved; (2) corrective steps which will be taken to avoid

further items of noncompliance; and (3) the date when full compliance will be

achieved.

,

l

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

l

10, Code of Federal Regulations, a copy of this letter and the enclosures will

be placed in the NRC's Public. Document Room.

If this report contains any infor-

mation that you (or your contractor) believe to be proprietary, it is necessary

that you make a written application within 20 days to this office to withhold

such information from public disclosure. Any such application must be accompanied

by an affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement of reasons

,

-

-~

,

.

.

Connecticut Yankee Atomic Power

2

FEB 2 5 1980

Company

which addresses with specificity the items which will be considered by the

Commission as listed in subparagraph (b) (4) of Section 2.790.

The infonnation

sought to be withheld shall be incorporated as far as possible into a separate

part of the affidavit.

If we do not hear from you in this regard within the

specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

f f

_ _&

-

E don J. Brunner, Chief

Reactor Operations and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement Inspection

Report Number 50-213/79-21

cc w/encls:

R. Graves, Plant Superintendent

D. G. Diedrick, Manager of Quality Assurance

J. R. Himelwright, Licensing Safeguards Engineer

.