Text
.-
<
g egg
UNITED STATES
o
NUCLEAR REGULATORY COMMts510N
[
'
o
REGION 1
3
$
631 PARK AVENUE
- I
f
KING OF PRUS$i A PENNSYLVANIA 19406
\\p* " * * /
FEB 2 8 1980
Docket Nos. 50-289
50-320
Hetropolitan Edison Company
ATTN: Mr. R. C. Arnold
Sr. Vice President
100 Interpace Parkway
Parsippany, New Jersey 07054
Gentlemen:
'
Subject:
Combined Inspection 50-289/79-24; 50-320/79-30
This refers to the inspection conducted by iiessrs. D. Haverkamp and
R. Conte of this office on November 28,1979 -January 4,1980, at Three
Mile Island Nuclear Station, Units 1 and 2, Middletown, Pennsylvania, of
activities authorized by NRC License Nos. DPR-50 and DPR-73 and to the
discussions of our findings held by Mr. Haverkamp with Mr. G. iiiller and
by Mr. R. Conte with Mr. J. Barton and other members of your staff at
the conclusion of the inspection.
Areas examined during this inspection period are described in the Office
of Inspection and Enforcement Inspection Report which is enclosed with
this letter. Within these areas, the inspection activities consisted of
selective examinations of procedures and representative records, interviews
with licensee and contractor personnel, measurements made by the inspectors,
and observations by the inspectors.
HRC personnel provided 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> per
day inspection coverage on site for all activities in progress except
routine shutdown evolutions not involving the movement or processing of
radioactive materials.
Within the scope of this inspection, no items of noncompliance were
observed.
In accordance with Section 2.790 of the NRC's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter and
the enclosures will be placed in the NRC's Public Docume..t Room.
If
this report contains any information that you (or your contractor)
believe to be proprietary, it is necessary that you make a written
application within 20 days to this office to withhold such information
from public disclosure. Any such application must be accompanied by an
affidavit executed by the owner of the information, which identifies the
document or part sought to be withheld, and which contains a statement
of reasons which addresses with specificity the items which will be
.
8004210097
,
.
.
FEB 2 8 1980
,
Metropolitan Edison Company
2
considered by the Cormiission as listed in subparagraph (b)(4) of Section
2.790. The information sought to be withheld shall be incorporated as
far as possible into a separate part of the affidavit.
If we do not
hear from you in this regard within the specified period, the report
will be placed in the Public Document Room.
No reply to this letter is required; however, should you have any questions
i
concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
~ TMt + N.
Ob.a
,
w Boyce H. Grier
f/' Director
Enclosure:
1.
Office of Inspection and Enforcement Combined Inspection Report
Numbers 50-289/79-24 and 50-320/79-30
cc w/encls:
'
J. G. Herbein, Vice President Nuclear Operations
R. F. Wilson, Director, TMI-2
R. Toole, Manager, TMI-1
J. J. Barton, Manager, Site Operations, TMI-2
W. E. Potts, Radiological Controls Manager, TMI-l
R. W. Heward, Radiological Controls Manager,.TMI.2
J. J. Colitz, Plant Engineering Manager, TMI-1
B. Elam, Plant Engineering Manager, TMI-2
L. W. Harding, Supervisor of Licensing
E. G. Wallace, Licensing Manager
I. R. Finfrock, Jr.
R. W. Conrad
G. F. Trowbridge, Esquire
J. B. Lieberman, Esquire
Ms. Mary V. Southard, Chairperson, Citizens for a Safe Environment (Without Report)
.