N UNITED STATES p gag f

o NUCLEAR REGULATORY COMMIS$10N o

REGION l

,g 631 PARK AVENUE I

KING OF PRUSSI A. PENNSYt VANIA 19406

%, *.... /

Docket No. 50-293 FE3 '2 7 W File No. IA1. 80-06 Boston Edison Company ATTN:

Mr. Carl Andognini, Manager Nuclear Operations Department 800 Boylston Street Boston, MA 02199 Gentlemen:

This refers to the telephone conversation between you and Mr. P. J. Knapp of this office on February 27, 1980, regarding our concerns for the emer-gency readiness posture at Pilgram Station.

With regard to the matters discussed in the referenced conversation, it is our understanding that the following actions will be undertaken and completed by the end of the current outage and prior to the resumption of operation of Pilgrim Station:

1.

Development of provisions to rapidly detect, measure and project radiation levels and radionuclide concentrations in air equivalent to the lower limits of the protective action guides for the general population adopted by the Commonwealth of Massachusetts.

2.

Development of action levels for declaring the various classes of emergencies listed in ycur emergency plan.

Such action levels are to be based upon readings frr. installed instrumentation as well as the results of the envir:nmental surveys and projections made in accordance with the provisions deeeloped per item 1.

3.

Review of all emergency plan implementing procedures with appropriate updating to correctly reflect:

existing types, locations and uses of facilities and equipment; notification means and telephone numbers on call lists; and the changes which will result from the completion of items 1 and 2.

1 Conduct appropriate training / retraining of all individuals assigned to 4.

the response organization and ensure that they are able to perform their assigned emergency duties in an effective manner.

5.

Perfonn a complete inventory and op9 rational check of all emergency equipment and facilities within 5 days and, in addition to any such checks which may be required by existing procedures, perfonn another no sooner than 3 days before restart.

l 3%5 8004090

ft 3

Boston Edison Company 2

rE3 2 71323 If our understandings as described above are not in agreement with your actual plans and actions being implemented, notify this office by telephone within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and in writing within 5 days.

Sincerely, W6 W Stfte ce H. Grier irector cc: