RO 77-51E:on 770509,marsh Grass Metabolism Sampling Deadline Overrun.Caused by Sampling Instrumentation Component Delivery Delay
ML19308D187
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 06/13/1977
From:
FLORIDA POWER CORP.
To:
Shared Package
ML19308D181 List:
References
NUDOCS 8002270654
Download: ML19308D187 (1)


Text

. .o:. .

ENVIRONMENTAL LICENSEE EVENT REPORT (77-51E) ,

1. Facility: Crystal River Unit #3 *
2. Report Date: 13 June 1977
3. Occurrence Date: 9 May 1977
4. Identification of occurrence:
The sampling ef fort for the matsh grass metabolisa-(producti-vity and respiration) studies was not completed within the first quarter sampling deadline.
5. Description of Occurrence:

The first quarter sampling deadline for CR #3 ETS nonradiologi-cal surveillance c(uarterly sampling was May 9,1977. The con-tractor (University of Florida) who is conducting the marsh .

maitabolism phase of the ETS studies over-ran this deadline by '

three days (sampling was completed on May 12, 1977). g

6. Designation of ;pparent. Cause of Occurrence:

Inability of the contractor to obtain certain components prior to 9 May 1977 for the sampling instrumentation was the cause of the delay.

7. Corrective Actic.' to Preclude Recurrence:

Inasmuch as parts are now installed, recurrence is not antici-paced.