Forwards LER 78-035/03L-0
Date released: 11/18/2019 Download: ML19308D155


LER 78-035/03L-0:on 780710,during Performance of SP-322, Cable Tunnel Pump Sump Operability Procedure,Two North Sump Pumps Failed to Start.Caused by Personnel Error in Securing Power to North Pumps at Substation.Switches to Be Tagged
ML19308D212
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 08/02/1978
From: Cooper J
FLORIDA POWER CORP.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19308D212 (2)
Forwards LER 78-035/03L-0
ML19308D154
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 08/04/1978
From: Stewart W
FLORIDA POWER CORP.
To: OREILLY J P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References