Text
5 O
DUKE POWER COMPANY (Oconee Nuclear Station, Unit 2)
DOCKET No. 50-270 ORDER EXTENDING COMPLETION DATE Duke Power Company is the holder of Provisional Construction Permit No. CPPR-34 issued by the Commission on November 6, 1967, for the con-struction of the Oconee Nuclear Station, Unit 2, a 2568 megawatt (thermal) pressurized water nuclear reactor presently under construction at the Company's site in Oconee County, South Carolina, approximately eight miles northeast of Seneca, South Carolina.
On August 29, 1973, the Company requested an extension of the com-pletion date because construction of Unit 2 has been delayed due to (1) diversion of construction forces from Unit 2 to Unit 1 to solve problems occasioned by the lateness of Unit 1, (2) delay in delivery of major reactor coolant components, and (3) modifications required to the reactor vessel internals for Unit 2.
The Director of Regulation having determined that this action involves no significant hazards consideration, and good cause having been shown, the bases for which are set forth in a memorandum dated September 21, 1973, from R. C. DeYoung to A. Giambusso.
IT IS HEREBY ORDERED ~THAT the latest completion date for CPPR-34 (Unit 2) is extended from October 1,1973 to November 4,1973.
FOR THE ATOMIC ENERGY COMMISSION Original Signed by A. Giambusso A. Giambusso, Deputy Director for Reactor Projects Directorate of Licensing Date of Issuance:
SEP 2 41973 I