O' APPENDIX A NOTICE OF VIOLATION Philadelphia Electric Company Docket No. 50-352 This refers to the inspection conducted by a representative of the Region I (Philadelphia) office at the Limerick Generating Station, Unit 1, Limerick, Pennsylvania, of activities authorized by NRC License No.
CPPR-106.
During this inspection conducted on October 15-31 and November 1-15, 1979, the following apparent items of noncompliance were identified:
A.
Appendix B, of 10 CFR 50, Criterion V, states in part: " Activities affecting quality...shall be accomplished in accordance with these instructions, procedures or drawings..."
The Limerick PSAR, Appendix D, Quality Assurance Program, Paragraph D.6.4 states, in part, that:
Bechtel Construction Department...is responsible for construction of the plant to approved engineering specifications, drawings, and procedures..."
Bechtel Power Corporation Job Rule G-7 Revision
, states in section 2.2, "in-place" is the location of equipment placed in the plant...because of surrounding construction work, it is during this period that the equipment is often least protected from dust, dirt and moisture. Temporary coverings, heating facilities and routine inspection shall be employed as specified on the maintenance action card.
Careful planning and surveillance is required to cnsure the equipment is adequately protected."
Contrary to the above, as of October 24, 1979 one end of the 4KV switchgear no.10All7 was not adequately protected from adjacent construction activities. There was raceway material, cable reels, empty soda cans and cement dust either next to or on the switchgear.
The scheduled surveillance activity for visual inspection was once per year, which is inadequate to ensure protection with the amount of construction activity present in the area. This item is an infraction.
OF B004230 L
Appendix A 2
B.
Appendix B. of 10 CFR 50, Criterion V, states in part: " Activities affecting quality...shall be accomplished in accordance with these instructions, procedures or drawings..."
The Limerick PSAR, Appendix D, Quality Assurance Program, Paragraph D.6.4 states, in part, that: Bechtel Construction Department...is responsible for construction of the plant to approved engineering specifications, drawings, and procedures..."
The heating, airconditioning and ventilation subcontractor's weld procedure SSM-502 Revision 3, states..."the welding current and manner of depositing the weld metal shall be such that there will be practically no undercutting into the base metal."
Contrary to the above, as of November 1,1979 excessive undercutting into the base metal resulted from the manner in which the welder deposited weld for the damper flange joint (FPD-202-47). The undercut exceeded 1/32 inch.
This item is an infraction.