UNITED STATES

o

NUCLEAR REGULATORY COMMisslON

y

o

REGION I

$

$

$31 PARK AVENUE

f

K!NG OF PRUSS8 A, PENNSYLVANIA 19406

%

,/

'

FEB 2 8 1980

Docket No. 50-293

Boston Edison Company M/C Nuclear

ATTN: Mr. G. Carl Andognini, Manager

Nuclear Operations Department

800 Boylston Street

Boston, Massachusetts 02199

Gentlemen:

Subject:

Inspection Report No. 50-293/80-04

This refers to the inspection conducted by Mr. David V. Kehoe of this

office on January 28-31, 1980 at Pilgrim Nuclear Power Station, Plymouth,

Massachusetts of activities authorized by NRC License No. DPR-35 and to

the discussions of our findings held by Mr. Kehoe with Mr. P. McGuire of

your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such information

from public disclosure. Any such application must be accompanied by an

affidavit executed by the owner of the infonnation, which identifies the

document or part sought to be withheld, and which contains a statement

df reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790. The information sought to be withheld shall be incorporated as

far as possible into a separate part of the affidavit.

If we do not

hear from you in this regard within the specified period, the report

will be placed in the Public Document Room.

l

8004160/45

__ _ _ _ _ _ _ _

_ __-________ _ __________ _

.

.

FEB 2 8 M

Boston Edison Company M/C Nuclear

2

No reply to this letter is required; however, if you should have any

questions conceraing this inspection, we will be pleased to discuss them

with you.

Sincerely,

4!;

Eldon J. Brunner, Ch

Reactor Operations and Nuclear

Support Branch

Enclosure: Office of Inspection and Enforcement Inspection

Report Number 50-293/80-04

cc w/ encl:

P. J. McGuire, Pilgrim Station Manager

.