Vino t NrA ELI:CTIt1C AND l'OWI:lt CO)11% N Y nzcismoxn vnnorw1A uned March 24, 1980 f
Mr. Harold R. Denton, Director Serial No. 259/031080 Office of Nuclear Reactor Regulation LQA/WRM:rab Atta: Mr D. F. Ross, Jr., Acting Director Division of Project Management Docket Nos. 50-338 U. S. Nuclear Regulatory Commission 50-339 Washington, D.C.
20555
Dear Mr. Denton:
A_UXILIARY FEEDWATER SYSTEM RELIABILITY NORTH ANNA UNIT 2 We have received your letter of March 10, 1980 regarding a generic request for information on auxiliary feedwater systems for all pending operating license applicants.
By our letter dated February 26, 1980 (Serial No. 151), we referenced our previous responses to NRC letters dated September 28, 1979 and December 14, 1979 concerning auxiliary feedwater systent requirements for North Anna Unit 1.
As noted in our letter of November 2, 1979 (Serial No. 825/092879), we are taking' action in response to the Staff's recommendations contained in the NRC reliability study of auxiliary feed-water systems at North Anna.
In addition, our November 2, 1979 letter noted that actions being taken will also be performed on Unit 2.
Accordingly,'the information you requested can be found in our previous responses referenced above.
Very truly yours, YWf
=
C. M. Stallings Vice President-Power Supply and Production Operations cc:
Mr. O. D. Parr, Chief Division of Project Management O