Notifies That NRC Has Issued Order Extending Facility Const Completion Date Until 841231 in Response to 790509 Request. Forwards Order,Nrc Safety Evaluation,Negative Declaration & Eia
ML19305B372
Person / Time
Site: Beaver Valley
Issue date: 01/30/1980
From: Stolz J
Office of Nuclear Reactor Regulation
To: Woolever E
DUQUESNE LIGHT CO.
Shared Package
ML19305B373 List:
References
NUDOCS 8003190593
Download: ML19305B372 (2)


Text

gf{

fhf

>" *n:e J

UNITED STATES

+

NUCLEAR REGULATORY COMMISSION

[

s, <

E WASHINGTON, O. C. 20555 t

o JAN 3 01980 Docket No: 50-412 Fr. E. J. Woolever Vice President Duquesne Light Canpany 435 Sixth Avenue Pittsburgh, Pennsylvania 15219

Dear Mr. Woolever:

SUBJECT:

ORDER EXTENDING CONSTRUCTION COMPLETION DATE (BEAVER VALLEY POWER STATION, UNIT N0. 2)

In response to your request of May 9,1979, the Nuclear Regulatory Commission has issued an Order extending the construction completion date for Beaver Valley Power Station, Unit No. 2.

In lieu of the latest completion date of February 1,1980, as specified in Construction Permit No. CPPR-105, the latest completion date has been extended to December 31, 1984.

A copy of the Order, the staff safety evaluation, negative declaration, and environmental impact appraisal are enclosed for your information. The Order and the negative declaration have been transmitted to the Office of the Federal Register for publication.

Si ncerely, Q

/

SNux. ----I Mid

/ John F. Stolz, Chief,)

Ljght Water Reactors 1 ranch No. 1 ivision of Project Management

Enclosures:

1.

Order Extending Completion Date 2.

Staff Safety Evaluation 3.

Negative Declaration 4.

Environmental Impact Appraisal cc:

See next page 80031005'93

o Mr. Earl J. Woolever cc: Gerald Charnoff, Esq.

Mr. C. O. Richardson, Jr.

Jay E. Silberg, Esq.

Stone & Webster Engineering Shaw, Pittran, Potts & Trowbridge Corporation 1800 M Street, N. W.

P. 0. Box 2325 Washington, D. C.

20036 Boston, Massachusetts 02107 Karin Carter, Esq.

Special Assistant Attor ey General Bureau of Administrative Enforcement Executive House - 5th Floor Harrisburg, Pennsylvania 17120 Mr. Joseph A. Fricker, Jr.

Utility Counsel City of Pittsburgh 313 City - County Building Pittsburgh, Pennsylvania 15219 Attorney General Department of Justice Capitol Annex Harrisburg, Pennsylvania 17120 Governor's Office of State Planning & Development ATTN: Coordinator, Pa. State Clearinghouse P. O. Box 1323 Harrisburg, Pennsylvania 17120 Mr. Thomas J. Czerpah, Mayor Burrough of Shippingport P. O. Box 25 Shippingport, Pennsylvania 15077 U. S. Environmental Protection Agency ATTN: EIS Coordinator Region III Office Curtis Building (Sixth Floor) 6th & Walnut Streets Philadelphia, Pennsylvania 19106 Mr. M. H. Judkis Westinghouse Electric Corporation Power Systems P. O. Box 355 Pittsburgh, Pennsylvania 15230 l

- - -