MONTHYEARIR 05000413/20230042024-02-0202 February 2024 Integrated Inspection Report 05000413-2023004 and 05000414-2023004 ML24005A2512024-01-26026 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) ML23233A1692023-08-17017 August 2023 EN 56683 - Curtiss Wright, Interim Notification Report for PotentialPurt2l IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined IR 05000413/20230012023-05-0505 May 2023 Integrated Inspection Report 05000413/2023001 and 05000414/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 ML23107A2542023-04-14014 April 2023 301 Examination Report Letter and Report (Merged) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20234012023-03-0101 March 2023 Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations IR 05000413/20224032022-11-17017 November 2022 Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22319A0942022-11-10010 November 2022 EN 56219 - Flowserve. 10 CFR Part 21 Report 38878-8 Solenoid Valve at Duke, Catawba Flowserve Evaluation 105 IR 05000414/20220032022-10-31031 October 2022 Integrated Inspection Report 05000414/2022003 and 05000414/2022003 IR 05000413/20224022022-10-28028 October 2022 Security Baseline Inspection Report 05000413 2022402 and 05000414 2022402 ML22297A2642022-10-25025 October 2022 Project Manager Assignment ML22276A2492022-10-25025 October 2022 Completion of License Renewal Commitment No. 10, Aging Management of Environmentally Assisted Fatigue ML22303A0052022-10-24024 October 2022 EN 56178 - Tioga Final. LTR-TP-22-29 2021 10CFR Part 21 Improper Notification of NRC ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22231B1362022-09-0101 September 2022 Review of the Draft Environmental Assessment and Findings of No Significant Impact for Catawba Nuclear Station, H.B. Robinson Steam Electric Plant, and Oconee Nuclear Station Independent Spent Fuel Storage Installation Decommissioning Fundi ML22303A0042022-08-31031 August 2022 Final Report Notification Pursuant to 10 CFR Part 21.21, Regarding Supply of 6 NPS Sch. 40 Seamless Stainless-Steel Pipe; Manufacturer: Maxim Tubes Company Pvt. Ltd.; Heat No: N200309AW01, SR No: 7; 9 Pcs; 180 Feet Total Procured as Unquali IR 05000413/20220052022-08-26026 August 2022 Updated Inspection Plan for Catawba Nuclear Station, Units 1 and 2 - NRC Inspection Report 05000413/2022005 and 05000414/2022005 ML22217A0792022-08-0303 August 2022 301, Corporate Notification Letter (210-day Ltr) IR 05000413/20220022022-07-29029 July 2022 Integrated Inspection Report 05000413/2022002 and 05000414/2022002 IR 07200045/20220012022-07-26026 July 2022 Operation of an Independent Spent Fuel Storage Installation Report 07200045/2022001 ML22215A2502022-07-25025 July 2022 EN 55960 - Update - Curtiss Wright IR 05000413/20220102022-07-21021 July 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000413/2022010 and 05000414/2022010 ML22195A2432022-07-19019 July 2022 Request for Withholding Information from Public Disclosure Regarding Reactor Vessel Closure Head Repair Alternative ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22199A2552022-07-0606 July 2022 Ds Catawba 2022 RQ Inspection Notification Letter ML22222A0092022-07-0101 July 2022 EN 55974 - Flowserve, Part 21 Report Re Solenoid Coil Failure of Model 38878-8 Solenoid Valve at Catawba Nuclear Station for Use on FWIV Actuator ML22175A0342022-06-28028 June 2022 Information Request for the Cyber-Security Baseline Inspection Notification to Perform Inspection 05000413/2022403 and 05000414/2022403 ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22111A3572022-05-16016 May 2022 Letter Issuing Exemption to Catawba IR 05000414/20220012022-04-28028 April 2022 Integrated Inspection Report 05000413/ 2022001 and 05000414/2022001 2024-02-02
[Table view] Category:License-Operator Examination Report
MONTHYEARML23116A1972023-04-26026 April 2023 301 2B ML23107A2542023-04-14014 April 2023 301 Examination Report Letter and Report (Merged) IR 05000413/20213012021-11-0808 November 2021 Operator Licensing Examination Report 05000413/2021301 and 05000414/2021301 ML19297E2292019-10-24024 October 2019 301 Exam Report Rev 0 IR 05000413/20153012015-07-13013 July 2015 Er 05000413/2015301, 05000414/2015301, Operating Test May 18 - 21, 2015 & Written Exam May 28, 2015; Catawba Nuclear Station; Operator License Examinations IR 05000413/20133012013-10-0808 October 2013 NRC Operator License Examination Report 05000413/2013301 and 05000414/2013301 ML12221A3912012-08-0606 August 2012 Duke Energy - Response to NRC Regulatory Issue Summary 2012-07 Preparation and Scheduling of Operator Licensing Examinations IR 05000413/20103012011-02-25025 February 2011 Er 05000413-10-301 and 05000414-10-301, on 12/13-17/10 - 12/21/10, Catawba Nuclear Station ML1115405252011-02-0202 February 2011 Initial Exam 2010-301 Final Simulator Scenarios ML1104102982011-02-0202 February 2011 Initial Exam 2010-301 Final SRO Written Exam ML1115700472011-02-0202 February 2011 Initial Exam 2010-301 Final Administrative JPMs ML1115404812011-02-0202 February 2011 Initial Exam 2010-301 Draft Administrative Documents ML1115404892011-02-0202 February 2011 Initial Exam 2010-301 Draft RO Written Exam ML1115404942011-02-0202 February 2011 Initial Exam 2010-301 Draft SRO Written Exam ML1115405092011-02-0202 February 2011 Initial Exam 2010-301 Draft Simulator Scenarios ML1115405152011-02-0202 February 2011 Initial Exam 2010-301 Draft Sim/IN-Plant JPMs ML1115405192011-02-0202 February 2011 Initial Exam 2010-301 Draft Administrative JPMs ML1115405222011-02-0202 February 2011 Initial Exam 2010-301 Final Administrative Documents ML1115700402011-02-0202 February 2011 Initial Exam 2010-301 Final Sim IN-Plant JPMs IR 05000413/20073012008-01-28028 January 2008 Er 05000413-07-301 & Er 05000414-07-301; on 12/03-06/2007 & 12/313/2007; Duke Power Co. Catawba Units 1 & 2, NRC Examination Report ML0734605652007-12-11011 December 2007 Oct 2007-301 Exam Approval Letter ML0711700042007-04-26026 April 2007 Er 05000413-07301, 05000414-07301, on 03/29/2007; Catawba Nuclear Station; Licensed Operator Examinations ML0701702592007-01-17017 January 2007 Operator Retake Initial Examinations - Catawba - 05000413/2007301 and 05000414/2007301 IR 05000413/20053012006-01-11011 January 2006 Er 05000413-05-301, 05000414/05-301; 12/5-12/8/2005 and 12/14/05; Catawba Nuclear Station, Units 1 and 2, Licensed Operator Examination ML0527602732005-09-21021 September 2005 Duke Power - Response to NRC Regulatory Issue Summary 2005-19 Preparation and Scheduling of Operator Licensing Examinations ML0220502652002-07-16016 July 2002 Response to NRC Regulatory Issue Summary 2002-09, Supplement Preparation and Scheduling of Operator Licensing Examinations 2023-04-26
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 October 24, 2019 Mr. Tom Simril Site Vice President Duke Energy Carolinas, LLC Catawba Nuclear Station 4800 Concord Road York, SC 29745
SUBJECT:
CATAWBA NUCLEAR STATION - NRC OPERATOR LICENSE EXAMINATION REPORT 05000413/2019301 AND 05000414/2019301
Dear Mr. Simril:
During the period of September 9 - 12, 2019, the Nuclear Regulatory Commission (NRC) administered operating tests to employees of your company who had applied for licenses to operate the Catawba Nuclear Station. At the conclusion of the tests, the examiners discussed preliminary findings related to the operating tests and the written examination submittal with those members of your staff identified in the enclosed report. The written examination was administered by your staff on September 19, 2019.
Three Reactor Operator (RO) and six Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. There were no post-administration comments concerning the written examination or the operating test. A Simulator Fidelity Report is included in this report as Enclosure 2.
The initial examination submittal was within the range of acceptability expected for a proposed examination. All examination changes agreed upon between the NRC and your staff were made according to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 11.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at (the Public Electronic https://www.nrc.gov/reading-rm/adams.html Reading Room).
T. Simril 2 If you have any questions concerning this letter, please contact me at (404) 997-4551.
Sincerely,
/RA/
Gerald J. McCoy, Chief Operations Branch 1 Division of Reactor Safety Docket Nos: 50-413, 50-414 License Nos: NPF-35, NPF-52
Enclosures:
- 1. Report Details
- 2. Simulator Fidelity Report
_ML19297E229 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS NAME MBATES GMCCOY DATE 10/ 18 10/ 24 /2019 E-MAIL COPY? /2019 YES NO YES NO U.S. NUCLEAR REGULATORY COMMISSION REGION II Examination Report Docket No.: 50-413, 50-414 License No.: NPF-35, NPF-52 Report No.: 05000413/2019301, 05000414/2019301 Enterprise Identifier: L-2019-OLL-0026 Licensee: Duke Energy Carolinas, LLC Facility: Catawba Nuclear Station, Units 1 & 2 Location: York, SC 29745 Dates: Operating Test - September 9 - 12, 2019 Written Examination - September 19, 2019 Examiners: M. Bates, Chief Examiner, Senior Operations Engineer J. Bundy, Operations Engineer M. Donithan, Operations Engineer Approved by: Gerald J. McCoy, Chief Operations Branch 1 Division of Reactor Safety Enclosure 1
SUMMARY
ER 05000413/2019301, 05000414/2019301; September 9 - 12, 2019 & September 19, 2019; Catawba Nuclear Station; Operator License Examinations.
Nuclear Regulatory Commission (NRC) examiners conducted an initial examination in accordance with the guidelines in Revision 11 of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." This examination implemented the operator licensing requirements identified in 10 CFR §55.41, §55.43, and §55.45, as applicable.
Members of the Catawba Nuclear Station staff developed both the operating tests and the written examination. The initial operating test, written Reactor Operator (RO) examination, and written Senior Reactor Operator (SRO) examination submittals met the quality guidelines contained in NUREG-1021.
The NRC administered the operating tests during the period of September 9 - 12, 2019.
Members of the Catawba Nuclear Station training staff administered the written examination on September 19, 2019. Three RO and six SRO applicants passed both the operating test and written examination. Nine applicants were issued licenses commensurate with the level of examination administered.
There were no post-examination comments.
No findings were identified.
2
REPORT DETAILS
- 4. OTHER ACTIVITIES 4OA5 Operator Licensing Examinations
- a. Inspection Scope The NRC evaluated the submitted operating test by combining the scenario events and Job Performance Measures (JPMs) in order to determine the percentage of submitted test items that required replacement or significant modification. The NRC also evaluated the submitted written examination questions (Reactor Operator (RO) and Senior Reactor Operator (SRO) questions considered separately) in order to determine the percentage of submitted questions that required replacement or significant modification, or that clearly did not conform with the intent of the approved knowledge and ability (K/A) statement. Any questions that were deleted during the grading process, or for which the answer key had to be changed, were also included in the count of unacceptable questions. The percentage of submitted test items that were unacceptable was compared to the acceptance criteria of NUREG-1021, Operator Licensing Standards for Power Reactors.
The NRC reviewed the licensees examination security measures while preparing and administering the examinations in order to ensure compliance with 10 CFR §55.49, Integrity of examinations and tests.
The NRC administered the operating tests during the period of September 9 - 12, 2019.
The NRC examiners evaluated three RO and six SRO applicants using the guidelines contained in NUREG-1021. Members of the Catawba Nuclear Station training staff administered the written examination on September 19, 2019. Evaluations of applicants and reviews of associated documentation were performed to determine if the applicants, who applied for licenses to operate the Catawba Nuclear Station, met the requirements specified in 10 CFR Part 55, Operators Licenses.
The NRC evaluated the performance or fidelity of the simulation facility during the preparation and conduct of the operating tests.
- b. Findings No findings were identified.
The NRC developed the written examination sample plan outline. Members of the Catawba Nuclear Station training staff developed both the operating tests and the written examination. All examination material was developed in accordance with the guidelines contained in Revision 11 of NUREG-1021. The NRC examination team reviewed the proposed examination. Examination changes agreed upon between the NRC and the licensee were made per NUREG-1021 and incorporated into the final version of the examination materials.
The NRC determined, using NUREG-1021, that the licensees initial examination submittal was within the range of acceptability expected for a proposed examination.
3
Three RO applicant and six SRO applicants passed both the operating test and written examination and were issued licenses.
Copies of all individual examination reports were sent to the facility Training Manager for evaluation of weaknesses and determination of appropriate remedial training.
The licensee submitted no post-examination comments concerning the operating test or the written examination. A copy of the final written examination and answer key, with all changes incorporated, may be accessed not earlier than November 3, 2021, in the ADAMS system (ADAMS Accession Numbers ML19281E017 and ML19281E019).
4OA6 Meetings, Including Exit Exit Meeting Summary On September 12, 2019, the NRC examination team discussed generic issues associated with the operating test with T. Simril, Site Vice President, and members of the Catawba Nuclear Station staff. The examiners asked the licensee if any of the examination material was proprietary. No proprietary information was identified.
On October 18, 2019, the NRC examination team discussed the results of the examination with B. Webster, Operations Training Supervisor, via telephone.
4
KEY POINTS OF CONTACT Licensee personnel T. Simril, Site Vice President B. Leonard, Training Manager B. Boyette, NRC Exam Developer R. Miller, NRC exam developer B. Webster, Initial License Training Supervisor NRC personnel J. Austin, Senior Resident Inspector 5
SIMULATOR FIDELITY REPORT Facility Licensee: Catawba Nuclear Station Facility Docket No.: 50-413, 50-414 Operating Test Administered: September 9 - 12, 2019 This form is to be used only to report observations. These observations do not constitute audit or inspection findings and, without further verification and review in accordance with Inspection Procedure 71111.11 are not indicative of noncompliance with 10 CFR 55.46. No licensee action is required in response to these observations.
No simulator fidelity or configuration issues were identified.
Enclosure 2