Text
fa arc
s
oq'o,
,
I
UNITED STATES
(
! " 3 ., , ( 3 'j
NUCLEAR REGULATORY COMMISSION
REGION 111
g
j-p
g
o,
g
799 ROOSEVELT ROAD
H
'
'\\/
j'
GLEN E LLYN, ILLINOIS 6o137
....
J:r
Docket No. 50-454
Docket No. 50-455
Commonwealth Edison Company
ATTN:
Mr. Cordell Reed
Vice President
Post Office Box 767
Chicago, IL 60690
Gentlemen:
This refers to the investigation conducted by Messrs. J. E. Foster and
P. A. Barrett of this office on August 28, September 27-28, October 11-12,
and November 5, 1979, of activities at the Byron Nuclear Generating
Station, Units 1 and 2, authorized by NRC Construction Permits No. CPPR-130
and No. CPPR-131 and to the discussion of our findings with Messrs. R. Akin,
G. Sorensen, and others of your staff at the conclusion of the investigation.
The enclosed copy of our investigation report identifies the areas examined
during the investigation. This investigation was conducted in response to
allegations by a former contractor QC engineer. Within the areas delineated
in the report, the investigation consisted of a selective examination of
procedures and representative records, observations, and interviews with
personnel.
During this investigation, certain of your activities appeared to be in
noncompliance with NRC requirements, as desem 3ed in the enclosed Appendix
A.
This notice is sent to you pursuant to the provisions of Section 2.201 of
the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office within thirty days of
your receipt of this notice a written statement or explanation in reply,
including for each item of noncompliance: (1) corrective action taken and
the results achieved; (2) corrective action to be taken to avoid further
noncompliance; and (3) the date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter, the enclosures,
and your response to this letter will be placed in the NRC's Public Document
Room, except as follows.
If the enclosures contain information that you
or your contractors believe to be proprietary, you must apply in writing
g()0229 0 0
I
'
Commonwealth Edison
-2-
Company
M,
to this office, within twenty days of your receipt of this letter, to
withhold such information from public disclosure. The application must
include a full statement of the reasons for which the laformation is
considered proprietary, and should be prepar
that proprietary informa-
- ion identified in the application is contai...
in an enclosure to the
.
application.
We will gladly discuss any questions you have concerning this investigation.
Sincerely,
n bN.
ames G. Kepple
l Director
Enclosure:
IE Investigation
Reports No. 50-454/79-18
and No. 50-455/79-18
cc w/ enc 1:
Mr. D. L. Peoples, Director
of Nuclear Licensing
Gunner Sorensen, Site
Project Superintendent