Requests Mod to FSAR Chapter 14 Test Description to Confirm That Testing of Some Distribution Sys & Transformers Supplying Power to Vital Buses Will Be Performed Per Reg Guide 1.68
ML19296C721
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 02/13/1980
From: Baer R
Office of Nuclear Reactor Regulation
To: Parker W
DUKE POWER CO.
References
RTR-REGGD-01.068, RTR-REGGD-1.068 NUDOCS 8002280003
Download: ML19296C721 (4)


Text

....

pa neg g'o,,

UNITED STATES l'

NUCLEAR REGULATORY COMMISSION

~

o h

WASHINGTON, D. C. 20S55 FEB 131980

+

Docket Nos. 50-369 and 50-370 Mr. William 0. Parker, Jr.

Vice President, Steam Production Duke Power Company P. O. Box 2178 422 South Church Street Charlotte, North Carolina 28242

Dear Mr. Parker:

SUBJECT:

STAFF POSITION: REGULATORY GUIDE 1.68, ' INITIAL TEST PROGRAMS FOR WATER-COOLED REACTOR POWER PLANTS" (McGuire Nuclear Station, Units 1 and 2)

It has come to our attention that some applicants did not intend to conduct con-fimatory tests of some distribution systems and transformers supplying power to vital buses as required by Position 3 of Regulatory Guide 1.68, and more specifi-cally by Part 4 of the staff position on degraded grid voltage. Part 4 of the

. degraded grid voltage position states as follows:

"4.

The voltage levels at the safety-related buses should be optimized for the full load and minimum load conditions that are expected throughout the anticipated range of voltage variations of the offsite power source by appro-priate adjustment of the voltage tap settings of the intervening transfomers. We require that the a Q uacy of the design in this regard be verified by actual measurement and by correlation of measured values with analysis results. Provide a description of the method for making this verification; before initial re. actor power operation, provide the documentation required to establish that this verification has been accomplished."

Your test description in FSAR Chapter 14 does not contain sufficient detail for us to detemine if yau intend to conduct such a test.

It is our position that confimatory tests of all vital buses must be conducted including all sources 8 0022 80QQ}

Mr. William 0. Parker, Jr. FEB 131960 of power supplies to the buses. Modify your test description to indicate that this testing will be conducted in accordance with Regulatory Guide 1.68 and the above cited position.

Sincerely, l*

Robert. L. Baer, Chief Light Water Reactors Branch No. 2 Division of Project Management ccs: See next pages

Mr. William 3. Parker, Jr.

fans is 1900 Vice President, Steam Production Duke Power Company P. O. Box 2178 422 South Church Street Charlotte, North Carolina 28242 cc: Mr. W. L. Porter Duke Power Company P. O. Box 2178 422 South Church Street Charlotte, North Carolina 28242 Mr. R. S. Howard Power Systems Division Westinghouse Electric Corporation P. O. Box 355 Pittsburgh, Pennsylvania 15230 Mr. E. J. Keith EDS Nuclear Incorporated 220 Montgomery Street San Francisco, California 94104 Mr. J. E. Houghtaling NUS Corporation 2536 Countryside Boulevard Clearwater, Florida 33515 Mr. Jesse L. Riley, President The Carolina Environmental Study Group 854 Henley Place

. Charlotte, North Carolina 28207 J. Michael McGarry, III, Esq.

Debevoise & Liberman 1200 Seventeenth Street, N. W.

Washington, D. C.

20036 Robert M. Lazo, Esq., Chairman Atomic Safety and Licensing Board U. S. Nuclear Regulatory Commission Washington, D. C.

20555 Dr. Emmeth A. Luebke Atomic Safety and Licensing Board U. S. Nuclear Regulatory Commission Washington, D. C.

20555 Dr. Cadet H. Hand, Jr., Director Bodega Marine Lab of Californie P. 0. Box 247 Bodega Bay, California 94923

a Mr. William 0. Parker, Jr.

FEB 131980

~

cc: David Flesichaker, Esq.

W 1735 Eye Street, N. W.,

Suite 709 Ir idshington, D. C.

20006 s

Richard P. Wilson, Esq.

1 Assistant Attorney General State of South Carolina 2600 Bull Street Columbia, South Carolina 29201 1-MI

_