ML19294B674
| ML19294B674 | |
| Person / Time | |
|---|---|
| Site: | Oconee |
| Issue date: | 01/24/1980 |
| From: | Bryant J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Parker W DUKE POWER CO. |
| Shared Package | |
| ML19294B675 | List: |
| References | |
| NUDOCS 8003050277 | |
| Download: ML19294B674 (2) | |
See also: IR 05000269/1980002
Text
-?q
!(#
o,,
UNITED STATES
NUCLEAR REGULATORY COMMISSION
ve do
/
o
3g
E
REGION 11
G7T
<
,
oy
[
101 MARlETTA ST
N.W.. SUITE 3100
'g __j_
ATLAf4TA. G ZoRGIA 30303
g*****
g
J AN 2 4 Y
In Reply Refer To:
RII:WPA
50-269/80-2
50-270/80-1
50-287/80-1
Duke Power Company
ATTN:
W. O. Parker, Jr.
Vice President, Steam Production
P. O. Box 2178
Charlotte, NC 28242
Gentlemen:
This refers to the inspection conducted by W. P. Ang of this office on January 9
through 11, 1980 of activities authorized by NRC Operating License Nos. DPR-38,
DPR-47 and DPR-55 for the Oconee Nuclear Station facility, and to the discussion
of our findings held with J. R. Wells at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspectors.
Within the scope of this inspection, no items of noncompliance were disclosed.
In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room. If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure. Any such application must
include a full statement of the reasons on the basis of which it is claimed that
the information is proprietary, and should be prepared so that proprietary infor-
mation identified in the application is contained in a separate part of the
document. If we do not hear from you in this regard within the specified period,
the report will be placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
J. C. B ant, Acting Chief
Reactor Construction and Engineering
Support Branch
Enclosure:
See Page 2
-
_
_
.
'
Duke Power Company
-2-
Enclosure:
Inspection Report Nos. 50-269/80-2
50-270/80-1 and 50-287/80-1
cc w/ encl:
J. E. Smith, Station Manager
P. O. Box 1175
Seneca, SC 29678
.