ML19294B583

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-546/79-25 & 50-547/79-25 on 791114-16 & 20. Noncompliance Noted:Failure to Provide Proper Storage & Maint of Matl
ML19294B583
Person / Time
Site: Marble Hill
Issue date: 01/14/1980
From: Harrison J, Williams C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19294B572 List:
References
50-546-79-25, 50-547-79-25, NUDOCS 8003050106
Download: ML19294B583 (6)


See also: IR 05000546/1979025

Text

'

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report Nos. 50-546/79-25; 50-547/79-25

Docket Nos. 50-546; 50-547

License No. CPPR-170; CPPR-171

Licensee: Public Service of Indiana

1000 East Main Street

Plainfield, IN 46168

Facility Name: Marble Hill Generating Station, Units 1 and 2

Inspection At: Marble hill Site

Inspection Conducted: November 14-16 and 20, 1979

Inspector:

J. J. Harrison

'

//[h[hO

/

/

Approved by:

C. C. Williams, Chief

/ / //.,(/ 9 C

'

Projects Section 2

/

'/

Inspection Summary

Inspection on November 14-16 and 20, 1979 (Report Nos. 50-546/79-25,

50-547/79-25.

Areas Inspected: Routine, unannounced inspection of the Auxillary Building,

Unit 1 and 2 containments, storage areas and miscellaneous areas to verify

that activities in progress complied with the stop work order issued August 7,

1979 and the adequacy of storage and maintenance of material (Units 1 and 2).

This inspection involved a total of 28 inspector hours on site by one inspec-

tor.

Results: Of the areas inspected one apparent item of noncompliance was

identified in one area (inf raction - failure to provide proper storage and

maintenance of material - Paragrapb 2).

f

B003050 \\ 00

.

DETAILS

Principal Persons Contacted

Public Service of Indiana (PSI)

  • L.

Crews, Vice President Construction

  • G.

Brown, Project Director (MAC)

  • J. Brewer, Construction Manager (MAC)

B. Turner, Quality Assurance Manager (MAC)

E. Shows, Consultant (MAC)

  • D. Ashley, Project Engineering Manager (MAC)
  • T. Burns, Project Engineering Manager

B. Roger, Area Engineer Reactor Building, Civil

  • R. Ubaudi, Project Controls Manager (MAC)

M. Morris, Project Controls Manager

T. Mclarty, Construction Inspection Supervisor

L. Shuter, Quality Engineer, Civil

-

G. Weston, Superintendent Mechanical Quality Engineer

R. Hand, Superintendent Electrical Quality Engineer (MAC)

J. Frost, Area Manager, Auxiliary Building (MAC)

J. Roberts, Superintendent Inspection

  • Denotes those present at the exit meeting.
    • (MAC) Management Analysis Company.

Authorized Nuclear Inspector

B. Rice, Hartford Steam Boiler (ANI-PSI)

Functional or Program Areas Inspected

1.

Construction Activities

Surveillance of construction activities indicated that work in all

Category I areas, i.e. , safety-related work, remains terminated, in

accordance with confirmatory order dated August 15, 1979, except for

material receiving, storage, and maintenance.

No items of noncompliance or deviations were identified.

2.

Storage and Maintenance of Material

The inspector observed the storage and maintenance of materials in lay-

down areas, warehouses, and in interim storage (installation process) in

the auxiliary and fuel handling buildings for compliance to the require-

ments of ANSI N45.2.2 - Packaging, Shipping, Receiving, Storage and Hand-

ling of Items for Nuclear Power Plants, the Nuclear Steam System Supplier -

Westinghouse and Public Service of Indiana's Management Manual for Con-

struction Procedures, specifically CMP 4.2.

The following observa'tions

were made.

-2-

.

a.

Storage Nonconformances:

-

(1) Neutron detector positioning device assembly stored outdoors

(Level D) in lieu of indoors (Level C) as required by

Westinghouse. This item had been improperly stored (outdoors)

for the past eighteen (18) months.

(2) Motor operated main steam isolation valves were stored outdoors

(Level D) in lieu of the required indoors (Level B).

These

valves have been incorrectly stored for the past ten (10)

months, although accept tags indicated Level B storage.

Ship-

ping containers were noted to be wet internally.

(3) Motor operated reactor coolant loop stop valves were stored

outdoors (Level D) in lieu of the required indoors (Level B).

These valves were received May 1978, Unit I and May 1979, Unit

2.

The Unit 2 shipping containers were noted to be wet in-

ternally. The attached accept tags indicated storage Level C

and the attached maintenance records indicated storage Level B.

These motor operated valves have been improperly stored for

eighteen months for Unit I and six months for Unit 2.

(4)

Instruments were improperly stored in a warehouse (Cherne-

Westinghouse), and not protected from damage.

Shipping

cartons for Masoneilan Instrument ILC-HD 241 to operate valve

1HD-054B and seventeen others were partially crushed / collapsed

and stacked in a haphazard manner. Visible damage, if any,

could not be determined.

(5) Residual heat removal cooler, 24A025A Elevation 346' fuel

handling building was observed to have a constant stream of

water several inches in diameter running directly onto the

unit. The unit although covered by a plastic tarp was wet

under the tarp.

(6) The protective end caps on the reactor coolant piping were

noted to be carbon steel and were rusty. The Westinghouse

equipment manual required these caps to be "non-ferrous

chloride free caps."

This piping was also noted not to be

covered by "a watertight covering," also a Westinghouse

requirement.

(7) The eight (8) reactor coolant pump casings are required to be

stored in a Level D area and are so stored. However, the

Westinghouse equipment manual states..." protected from the

elements..."; these pump casings were currently stored with

no protective covering.

(8) The reactor coolant piping (stainless steel) was also noted

to have carbon steel banding materials attached and due to

the protective cardboard that has deteriorated is causing

rust discoloration and possible corrosion transfer on the

-3-

.

'

stainless surface. The Westinghouse equipment manual states

..." stainless steel material must not be in contact with carbon

steel."

(9) Two boxes of "0" rings (10 sets) for the reactor vessel to

reacte- head seals were currently stored outdoors, Level D.

Th. '

0" rings are required by ANSI N45.2.2 to be Level B

storage. The storage boxes are currently wet and although

covered by a plastic tarp are not properly protected.

(10) The Westinghouse equipment manual requires that tanks, filters,

demineralizers, and auxiliary heat exchangers that are to

be stored in Level D areas to be:..."under a flame-resistant,

weatherproof covering.

Covering is to be placed to provide

drainage and permit air circulation to minimize condensation.

No wrap or covering is to be placed directly on equipment...".

Contrary to the above, a total of fourteen demineralizers (e.g.

thermal regeratioregeneration and spent fuel pit), eight

auxiliary heat exchangers (e.g. residual heat removal and

chemical volume contrul', and twelve tanks.

For example:

The Boron injection tanx, Boron injection surge tank and

the volume control tanks were noted to be stored in Laydown

area No. 26 with no covering. Some of those components have

been on site since 1978.

(11) The reactor coolant system supports were stored outdoors, Level

D, as required; however, the waterproof covering required by

the Westinghouse equipment manual was not being utilized.

b.

Maintenance Monconformances

(1) The neutron detector positioning device assembly required by

the Westinghouse equipment manual to have various types of

maintenance performed at receipt and annually thereaf ter.

Although this assembly has been on site since June 1978

no maintenance had been performed.

(2) The purge pressure on the steam generators and pressurizer

has not been maintained within tae recommended 3-5 psi range

requireu by Westinghouse. Readings were noted by the inspector

to be as low as 1/2 psi and as high as 11 psi. Westinghouse

further recommends..."that gas (nitrogen) cylinders remain

connected and open, thus enabling a continuous purge in the

event of a seal leak."

Purge seal leakage is evident through

review of maintenance records for some of these components.

It

is further required that the dew point be measured (In - 60 F

and Out - 20 F) and oxygen measured (In - less than 100 ppm

and Out - less than 500 ppm); these measurements were not being

taken.

(3) The protective coatings on the four steam generators, (Unit 1),

two reactor vessels, (Units 1 and 2), and one pressurizer

-4-

.

(Unit 1) were damaged during shipment and handling. The

unprotected areas were noted to be rusting ar.d were brought

to the attention of the licensee on numerous occasions but

no timely action was taken.

(4) The desiccator plughumidity indicator reading for the reactor

vessel exceeds 80 percent for Unit 1 and 50 percent for Unit 2.

The Westinghouse equipment manual requires (a) these readings

be checked and recorded in a monthly log and (b) if the readings

exceed 50 percent regenerate or replace the desiccant, neither

of the foregoing requirements had been met.

These conditions

had existed for the last three months.

(5) Although the motor heaters on various equipment (components)

were noted to be energized during this inspection, conditions

existed that defeated the heater purpose, to eliminate damaging

moisture. Examples of these conditions were:

(a) Reactor coolant loop stop valves and main steam isolation

valves being stored outdoors: the shipping crates were

wet internally, thus creating a damp environment.

(b) The eight residual heat removal coolers located in the

fuel handling building (elevation 346' are stored above

several inches of water with the protective coverings

draped to water. Again, a damp / wet environment.

(6) The maintenance records (on the equipment) for the nitrogen

purge on the Let-down heat exchangers for Units 1 and 2

indicated that the purge reading had not been verified as

required (weekly) as follows:

(a) The Unit 1 purge had not been verified during the last

three weeks.

(b) The Unit 2 !arge had not been verified since the heat

exchanger was received on site in June, 1978.

(7) The protective caps and seals on various tanks were missing

or not properly installed, examples:

(a) Reactor coolant drain tank, nozzle protective caps not

sealed.

(b) Volume control tank, protective cap missing and other

protective caps not sealed.

(8) The nuts, bolts and studs of the three residual heat removal

heat exchangers, the two chemical chemical and volume control

heat exc'tangers, and the volume control tank were noted to be

rusty aoJ not protected. The Westinghouse equipment manual

requir<a application of a lubricant or paint to protect

-5-

.

'

and to prevent rusting should outdoor (Level D) storage be

utilized; these components were stored in a Level D area.

It is apparent from the observations made and the numerous examples

listed that the material control program lacks sufficient control to

adequately prevent damage or deterioration. Also, it is evident that

adequate planning was not accomplished in providing correct levels of

storage and sufficient space to house the material in those areas; lack

of this control was identified by the NRC in 1978.

It is further evident

that a maintenance program has not been carried out to afford the pro-

tection required.

Based on these issues, it is concluded that PSI has

not satisfactorily implemented this part of its quality assurance pro-

gram. This is contrary to 10 CFR 50, Appendix B, Criterion XIII.

(546/79-25-01 and 547/79-25-01).

Exit Interview

The inspector met with those persons deliniated in the " Persons Contacted"

Paragraph of this report at the conclusion of the inspection. The inspec-

tor summarized the scope and findings of the inspection.

-6-