Forwards IE Insp Rept 50-483/78-14 on 781204-06.No Noncompliance Noted
ML19294A743
Person / Time
Site: Callaway Ameren icon.png
Issue date: 02/01/1979
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Bryan J
UNION ELECTRIC CO.
Shared Package
ML19294A744 List:
References
NUDOCS 7903130030
Download: ML19294A743 (2)


See also: IR 05000483/1978014

Text

I

'*g""

o

UNITED ST ATES

1

5

NUCLL Ah REGULA10RY COMMISSIO'

$Y

E

R E GION .. '

5 . h,,,Y[

Y

F

..

.i,nr.

v.1,

6 -. -

-

m,.

.

.

.m.

..

.

.

,

T.

...

Docket No. 50-483

Union Electric Company

ATTN:

Mr. John K. Bryan

Vice President - Nuclear

Post Of fice Box 149

St. Louis, MO 63166

Gentlemen:

This refers to the inspection conducted by Messrs. E. R. Schweibinz

and W. A. Hansen of this office and J. Mattia of the Region I Office

of Inspection and Enforcement on December 4-6, 1978, of activities at

the Callaway Unit 1 construction site authorized by NRC Construction

Permit No. CPPR-139 and to the discussion of our findings with Mr. Weber

and others of the Callaway staff at the conclusion of the inspection.

The enclosed copy of our inspection repcrt identifies areas

examined during the inspection. Within these areas, the

inspection consisted of a selective examination of procedures

and representative records, observations, and interviews with

personnel.

No items of noncompliance with NRC requirements were identified

during the course of this inspection.

During this inspection we noted that your response to NRC Circular

No. 76-02 (Westinghouse BF and BFD relays) was not adequately

supported with regard to the use of these relays in those

safety related systems that are not in the Westinghouse NSSS scope

of supply. A commitment was made to provide a revised response. We

have received your revised response dated December 14, 1978, and

determined it to be acceptable.

In accordance with Section 2.790 of the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this

letter and the enclosed inspection report will be placed in the

NRC's Public Document Room, except as follows.

If this report

contains information that you or your contractors believe to be

proprietary, you must apply in writing to this office, within

7903130030

.

.

Union Electric Company

-2-

twenty days of your receipt of this letter, to withhold such

information from public disclosure.

The application must include

a full statement of the reasons for which the information is con-

sidered proprietary, and should be prepared so that proprietary

information identified in the application is contained in an

enclosure to the application.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

',

s'

R. F. Heishman, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection

Report No. 50-483/78-14

cc w/ encl:

Mr. W. H. Weber, Manager

Nuclear Construction

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

/ TIC

Regions I & IV

Ms. K. Drey

Hon. C. J. Frass, Chairman

Missouri Public Service