Text
'
Qsuum SACRAMENTO MUNICIPAL UTILITY DISTRICT C 6201 s street, Box 15830, Sacramento, California 95813; (916) 452 3211 January 16, 1980 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C.
20555 Docket 50-312 Rancho Seco Nuclear Generating Station, Unit 1
Dear Mr. Denton:
Please find enclosed the Sacramento Municipal Utility District's answer to Order to Show Cause which you issued on January 2, 1980. Rancho Seco Nuclear Generating Station is presently shut down and will remain shut down for its annual refueling and maintenance outage originally scheduled to begin January 19, 1980.
The District desires at this time to set forth appropriate documentary justification for delays in implementation of the " Category A" short-term lessons learned requirements due to the unavailability of equipment of which the District is currently aware.
Signal processing equipment required for the implementation of Item 2.1.3.a is not expected to be delivered until May 1,1980, which is after the scheduled startup date for Rancho Seco. The period November 1 through December 7,1979 was required for the preparation of specifications for this equipment. The specifications were released fcr bid on December 7, 1979 and the bid opening was on December 26, 1979. The District's Board of Directors rejected all bids on January 3,1980, and authorized the General Manager to negotiate a contract for this material. Negotiations were completed and District Contract Number 7504 was awarded on January 7, 1980 to Technology Energy Corporation.
Equipment to be located within the reactor building will be delivered by approximately March 1,1980 and should be installed during this outage.
The delivery of equipment to be located outside the reactor
[OY/
building (signal processing equipment) is presently scheduled for 5
April 15, 1980. This date is based on tha best production schedule avail-j[
noo:
un H. Desroa j j 8001230 log 2
u
Mr. Harold R. Denton January 16, 1980 able at this time, and the District finds it reasonable to expect delivery on May 1, 1980.
If we can provide any additional information, please advise.
Sincerely, 1 'j u T u m
~[ John [ Mattimoe Assistant General Manager and Chief Engineer Enclosure cc: Thomas A. Baxter Elizabeth S. Bowers Dr. Richard F. Cole Mr. Frederick J. Shon Stephen H. Lewis Gary Hursh Mr. Richard D. Castro Michael H. Remy Christopher Ellison Lawrence Coe Lanpher Docketing and Service Section, flRC 7 q -(>
- t. - -
,,