Forwards Draft Suppl to Fire Protection Safety Evaluation. Incomplete Items Identified in 780303 Safety Evaluation, Section 3,acceptably Resolved,Provided Proposed Mods Implemented.Item 3.2.5 to Be Addressed in Further Suppl
ML19290E559
Person / Time
Site: Oyster Creek
Issue date: 01/31/1980
From: Lainas G
Office of Nuclear Reactor Regulation
To: Ziemann D
Office of Nuclear Reactor Regulation
Shared Package
ML19290E560 List:
References
NUDOCS 8003140207
Download: ML19290E559 (2)


Text

&$

h00

~

f%,

y UNITED STATES g

f e(

g NUCLEAR REGULATORY COMMISSION C

WASH 6NGTON, D. C. 20555

..s. -/

\\.

J A f. d 1 IS 8 C MEMORANDUM FOR: Dennis"L. Ziemann, Chief, Operating Reactors Branch #2, Division of Operating Reactors FROM:

G. Lainas, Chief Plant Systems Branch, Division of Operating Reactors

SUBJECT:

SAFETY EVALUATION REPORT (SER), FIRE PROTECTION PROGRAM REVIEW - OYSTER CREEK (TAC 11104)

Plant Name: Oyster Creek Nuclear Generating Station Licensee: Jersey Central Power and Light Company Docket No.: 50-219 Project Manager:

S. Nowicki Status: See Enclosure 1.

Our initial SER dealing with fire protection at the Oyster Creek facility was issued on March 3, 1978. In Section 3 of the SER, certain items were identified as incomplete and requiring further information from the licensee and evaluation by the staff. We have completed our review of infonnation dealing with these incomplete items as provided in licensee responses of April 7 (2 letters), August 1 and Septerrber 22, 1978; August 31 and December 7,1979.

The results of our review are described in the enclosed Draft Supplement to the SER (Enclosure 2). We find that the incomplete items have been acceptably resolved subject to the implementation of proposed modifications with the exception of item 3,2,5 from our SER.

Item 3.2.5 will be addressed in a further supplement following completion of the alternate shutdown system as part of the systematic evaluation program.

Fire Protection engineering assistance was provided for this review by DSS, lYlM

' G, Lainas, Chief Plant Systems Branch Division of Operating Reactors

Contact:

H. George, X??'s6

?

8003140 Nh

0YSTER CREEK FIRE PROTECTION REVIEW STATUS Licensee Item Staff Evaluation Response Due 3.1.4 Fire Detectors Complete NONE 3.1.5 Halon Suppression Systems Complete NONE 3.1.6 Water Spray Systems Complete NONE 3.1.7 Sprinkler Systems Complete NONE 3.1.16 Ventilation System Changes Complete NONE 3.1.20 Alternate Water Supply Complete NONE 3.1.21 Protection From Water Damage Complete NONE 3.1.22 New Battery Room and Rerouting of Complete NONE Battery Cables 3.1.23 Remote Shutdown Station (SEP)

After design for SEP 3.2.1 Administrative Controls Complete NONE 3.2.2 Radwaste Fires Complete NONE 3.2.3 Fire Barrier Penetrations Complete NONE 3.2.4 Comunications Equipment Complete NONE 3.2.5 Fire Hazards Analysis Update (SEP)

After alternate shutdown design for SEP

.w--