Forwards LER 79-007/03L-0,LER 79-008/03L-0,LER 79-009/03L-0, LER 79-010/03L-0, & 79-011/03L-0
Date released: 10/24/2019 Download: ML19283B767


LER 79-011/03L-0 on 790221:while Doing FNP-1-STP-28.7,LOSP B1F Sequencer Failed to Meet Time Requirement for Picking Up Step 6.Caused by Agastat Timer Setpoint Drift.Agastat Timer Adjusted & Satisfactorily Retested
ML19283B776
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 03/14/1979
From: Hairston W
ALABAMA POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19283B776 (1)
LER 79-010/03L-0 on 790218:while Doing FNP-1-STP-215.1B, Steam Flow/Feed Flow Bistable (FB478A)failed to Meet Table 2-1 Trip Setpoint Valve.Caused by Bistable Setpoint Drift Below That Specified in Surveillance Test.Bistable Adjusted
ML19283B775
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 03/14/1979
From: Hairston W
ALABAMA POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19283B775 (1)
LER 79-009/03L-0 on 790216:during Plant Startup W/Reactor & Steam Generator Controls Manual & Steam Dumps in Automatic, Steam Dumps Occurred.Temp Average Reduced to 538 F.Personnel Reinstructed
ML19283B774
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 03/14/1979
From: Hairston W
ALABAMA POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19283B774 (1)
LER 79-008/03L-0 on 790216:during Review of Surveillance Test FNP-1-STP-15.0,containment Main Personnel & Emergency Air Leak Outer Doors Failed to Meet Acceptance Criteria. Leakage Probably Caused by Dirty Door Seals &/Or Seal Set
ML19283B771
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 03/14/1979
From: Hairston W
ALABAMA POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19283B771 (3)
LER 79-007/03L-0 on 790212:during Review of Surveillance Test Data,Noted That RCS Leakage Test (FNP-1-STP-9.0) Had Not Been Done within Time Specified.Caused by Personnel Failure.Supervisors Instructed Re Matter
ML19283B770
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 03/14/1979
From: Hairston W
ALABAMA POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19283B770 (1)
Forwards LER 79-007/03L-0,LER 79-008/03L-0,LER 79-009/03L-0, LER 79-010/03L-0, & 79-011/03L-0
ML19283B766
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 03/14/1979
From: Clayton F
ALABAMA POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
Download: ML19283B766 (1)