Forwards IE Insp Rept 50-385/78-32 on 781228-29 & Notice of Violation
ML19282B924
Person / Time
Site: Zimmer
Issue date: 02/01/1979
From: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Borgmann E
CINCINNATI GAS & ELECTRIC CO.
Shared Package
ML19282B925 List:
References
NUDOCS 7903190035
Download: ML19282B924 (2)


See also: IR 05000385/1978032

Text

,*

.

e

,

.

4

.O

%

t rJITL D i,T A T E C

[,

9

+

NtICIFA r. Dr( ' ' ^ ' ' ) r' Y COMMKSf 0:

-

j Q , ;d: $

RE Glo:. lli

%

.!

J-

Q

c.

, w

Docket No. 50-358

Cincinnati Gas and Electric

Company

ATTN:

hk. Earl A. Borgmann

Vice President

Engineering Services

and Electric Production

139 East 4th Street

Cincinnati, OH 45201

Gentlemen:

This refers to the inspection conducted by Mr.

I. T. Yin of

this office on December 28-29, 1978, of activities at the

William H. Zimmer Power Station authorized by NRC Construction

Permit No. CPPR-88 and to the discussion of our findings with

Mr. B. K. Culver and others of your staff at the conclusion of

the inspection.

The enclosed copy of our inspection report identifies areas

examined during the inspection. Within these areas, the

inspection consisted of a selective examination of procedures

and representative records, observations, and interviews with

personnel.

During this inspection, certain of your activities appeared

to be in noncompliance with NRC requirements, as described

in the enclosed Appendix A.

This notice is sent to you pursuant to the provisions of

Section 2.201 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations.

Section 2.201 requires you

to submit to this office within thirty days of your receipt

of this notice a written statement or explanation in reply,

including for each item of noncompliance: (1) corrective

action taken and the results achieved; (2) corrective action

to be taken to avoid further noncompliance; and (3) the date

when full compliance will be achieved.

7 90319 00?> S-

.

.

.

'.

Cincinnati Gas and Electric

-2-

Company

In accordance with Section 2.790 of the NRC's " Rules of

Practice," Part 2, Title 10, Code of Federal Regulations, a

copy of this letter, the enclosures, and your response to

this letter will be placed in the NRC's Public Document Room,

except as follows.

If the enclosures contain information

that you or your contractors believe to be proprietary, you

must apply in writing to this office, within twenty days of

your receipt of this letter, to withhold such information

from public disclosure. The application must include a full

statement of the reasons for which the information is con-

sidered proprietary, and should be prepared so that proprietary

information identified in the application is contained in an

enclosure to the application.

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

M

wu '

h-

R. F. Heishman, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection

Rpt No. 50-358/78-32

cc w/ encl:

J. R. Schott, Plant Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

U. Young Park, Power Siting

Commission