ML19281A463

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Rept 50-245/78-40 on 781220-21.No Noncompliance Noted
ML19281A463
Person / Time
Site: Millstone 
Issue date: 01/26/1979
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Counsil W
NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML19281A465 List:
References
NUDOCS 7903140356
Download: ML19281A463 (2)


See also: IR 05000245/1978040

Text

'

"%

UNITED STATES

4

&

&

NUCLEAR REGULATORY COMMISSION

[ IC 4A.kZh

$

REGION I

3

A

f

G31 PARK AVENUE

i

KING OF PRUS$1 A, PENNSYLV ANI A 19406

JAN 2 6 W

Docket No. 50-245

Northeast Nuclear Energy Company

ATTN: Mr. W. G. Counsil

Vice President - Nuclear

Engineering and Operations

P. O. Box 270

Hartford, Connecticut

06101

Gentlemen:

Subject:

Inspection 50-245/78-40

This refers to the inspection conducted by Mr. E. P. Jernigan of this

office on December 20-21, 1978 at Millstone Point Nuclear Generating

Station, Unit 1, Waterford, Connecticut of activities authorized by NRC

License No. DPR-21 and to the discussions of our findings held by Mr.

Jernigan with Mr. J. F. Opeka and other members of your staff at the

conclusion of the inspection.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such information

from public disclosure. Any such application must be accompanied by an

affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement

of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790. The information sought to be withheld shall be incorporated as

far as possible into a separate part of the affidavit.

If we do not

hear from you in this regard within the specified period, the report

will be olaced in the Public Document Room.

7903y49 g(o

-

.

,

Northeast Nuclear Energy Company

2

No reply to this letter is required; however, should you have any ques-

tions concerning this inspection, we will be pleased to discuss them

with you.

Sincerely,

M


.

Robert T. Carlson, Chief

'

Reactor Construction and Engineering

Support Branch

Enclosure:

Office of Inspection and Enforcement Inspection

Report Number 50-245/78-40

cc w/ encl:

J. F. Opeka, Station Superintendent

D. G. Diedrick, Manager of Quality Assurance

J. R. Himmelwright, Licensing Safeguards Engineer

A. Z. Roisman, Natural Resources Defense Council (Without Report)