ML19281A427

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-327/79-02 on 790103-05.No Noncompliance Noted.Major Areas Inspected:Witnessing Preoperational Test TVA-13B(2),review of Applicant Response to Previous Items & Plant Tour
ML19281A427
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 01/24/1979
From: Donat T, Martin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19281A421 List:
References
50-327-79-02, 50-327-79-2, NUDOCS 7903130214
Download: ML19281A427 (5)


See also: IR 05000327/1979002

Text

.L.,,

  1. [g8"%gjo,,

UNITED STATES

,

NUCLEAR REGULATORY COMMISSION

,

o

REGION 11

$

101 M ARIETTA sTR E ET, N.W.

5

-

o

~ #

ATLANTA, GEORGI A 303o3

%,...../

Report No.: 50-327/79-02

Docket No.: 50-327

License No.:

CPPR-72

Licensee: Tennessee Valley Authority

830 Power Building

Chattanooga, Tennessee 37401

Facility Name:

Sequoyah, Unit 1

Inspection at: Sequoyah Site, Daisy, Tennessee

Inspection conducted: January 3-5, 1979

Inspectors:

T. J. Donat

Approved by:

'/E Y

R. D. Martin, Chief

'Date

Nuclear Support Section No. 1

Reactor Operations and Nuclear Support Branch

Inspection Summary

Inspection on January 3-5, 1979 (Report No. 50-327/79-02)

Areas Inspected:

Routine, announced inspection consisting of witnessing

preoperational test TVA-13B(2) (Loss of Off-Site Power), review of appli-

cant response to previously identified items, and facility tour. The

inspection involved 28 inspector-hours on-site by one NRC inspector.

Results: Of the three areas inspected, no items of concompliance or

deviations were identified.

!

7 90313 0 J/f

.L ,

, . . ~ . .

.

.

",

RII Rpt. No. 50-327/79-02

I-1

DETAILS I

Prepared by:

7

T. J. Donat, Reactor Inspfctor

' Date

Nuclear Support Section No. 1

Reactor Operations and Nuclear

Support Branch

Inspection Dates: Ja ary 3-5, 1979

Reviewed by:

[W/77

R. D. Martin, Chief

Date

Nuclear Support Section No. 1

Reactor Operations and Nuclear

Support Branch

1.

Persons Contacted

Tennessee Valley Authority (TVA)

  • W. F. Popp, Assistant Plant Superintendent
  • W. E. Andrews, Plant Quality Assurance Staff Supervisor
  • E. A. Condon, Preoperational Test Supervisor

W. Guinn, Operation Supervisor

R. H. Smith, Electrical Engineer

F. Siler, Instrument Engineer

P. Garrett, Nuclear Engineer

R. G. McCall, Mechanical Engineer (Engineering, Knoxville)

J. Lyons, II, Nuclear Engineer (Engineering, Knoxville)

  • Denotes those present at the exit interview.

2.

Licensee Action on Previous Inspection Findings

a.

In IE Report 50-327/78-04, Detail

I.5.b.2.b,

the inspector

identified that the maximum initial ice load weight used in

FSAR section 5.6.1 (Ice Condenser Refrigerator System Design

Basis) was inconsistant with the maximum values specified in

preoperational test W-12.1 (Ice Condenser Reactor Containment -

Rev. 0) step 5.3.1 and Special Maintenance Instruction SNP-

SMI-1-61-1 being used to load the Unit #1 Ice Condenser.

Ammendment 56 to the FSAR has revised the maximum Initial Ice

Load weight to 3.01 X 10s Ibm which is consistent with the

maximum weights used in W-12.1 and SNP-SMI-1-61-1.

This item

f

(78-04-04) is considered closed.

.

e%

-

. - . . .

- . . _ _ .

._

_

_

,

,

RII Rpt. No. 50-327/79-02

I-2

b.

In IE Report 50-327/78-17, Detail I.5 and 50-327/78-45, Detail

I.6.A,

discussed the commitments to monitor the Pressurizer

Relief piping downstream of the valves during the Hot Func-

tional Test Program.

On January 9,

1979, the applicant con-

tacted the inspector to discuss his program.

The applicant

stated that for safety reasons, a program of inspection prior

to and following the transients would be implemented.

He

stated that observers will be positioned on the containment

floor to observe as much pressurizer relief piping as possible

during the pressurizer blowdown and the procedure will be

modified to achieve this to a degree consistent with safety.

The inspector stated that a similar program of inspection of

piping, restraint, hangers, snubbers, and adjacent piping

prior to and subsequent to pressurizer relief lifting had been

found acceptable at other sites. The inspector stated that he

would review the final program as implemented in preoperational

test W-1.3 and would consider the item open until that time.

c.

In IE Reports 50-327/78-21, Detail

I.7,

and 50-327/78-35,

Detail I.8.b identified the need to verify the Diesel Gen-

erator's response in the event it is running and paralleled

with the normal power source when the site experiences a lo::s

of offsite power. The applicant has written a new preoperational

test procedure, TVA-13D Rev. 0 (Blackout with Diesel in Test

Mode), to verify the response.

The inspector has reviewed the

test procedure for conformance to the requiremer.ts of FSAR

Section 8.3.1.1 and Table 14.1, and Regulatory Guide 1.68.2,

1.41 and 1.108 and found no discrepancies. The inspector also

reviewed the calibration sheets for the diesel generator's

"51V Voltage Controlled Overcurrent Relays" to be utilized

during this test.

The preoperational test procedure TVA-13D

satisfies the concerns in open item (78-21-03).

This item is

considered closed.

3.

Unresolved Items

None

4.

Exit Interview

The inspector met with Mr. W. F. Popp concerning the inspection

on January 5,1979. The inspection lasted beyond the exit interview

,

and a call was placed to Mr. E. A. Condon on January 10, 1979, to

state that no additional findings were made af ter the exit interview.

The inspector summarized, as reported in the following paragraphs the

.t

. . _ _ _ . _ _ _ . . _. _

.. _

__

,

'.

RII Rpt. No. 50-327/79-02

I-3

purpose and findings of the inspection. Within the areas inspected

no items of noncompliance or deviations were identified.

5.

Preoperational Test Witnessing

The inspector witnessed the performance of portions of preoper-

ational test procedures W-6.1A1 (SIS - Integrated Flow), and TVA-

13B(2) (Onsite AC Distribution - Loss of Offsite Power).

a.

The inspector witnessed the repetition of those portions of

W-6.1A1 necessary to obtain new data in place of the out-of-

specification RHR pump suction data discussed in IE report

50-327/78-45, detail

I.6.

It was noted that the appropriate

prerequisites had been re-signed, the chronological test log

was being used, and the official copy of the test procedure

was being used.

A review of the test data showed a disagreement, when all

pumps were secured, between the suction pressures recorded for

the RHR pumps and those for the containment spray pumps which

are located on the same elevation.

The applicant stated that

this was due to leakage past RHR pump discharge throttle

valves FCV-74-16 and FCV-74-23.

Subsequent closure of down-

stream valves FCV-63-93 and 63-94, securing gravity flow past

the discharge valves, resulted in RHR suction pressures which

were within specification and which agreed within measurement

accuracy with the containment spray pump suction pressures.

The inspector witnessed the performance of the portion of

paragraph 5.2 concerning the vibration of the RHR train when

in the recirculation mode.

Witnessed were the measurement of

vibration levels on RHR heat exchanger IB-B discharge piping

and the tracing of the piping associated with RHR train B while

monitoring it for excessive vibration.

The inspector did not

have any comments concerning the conduct of the test and

vibration measurement by the applicant.

b.

The inspector witnessed the performance of portions of TVA-

13B(2) - Onsite AC Distribution Test (Loss of Offsite Power). Prior to

and during the test the inspector reviewed the test prerequisite

section, section

2., to insure that all items had been signed by

the appropriate personnel. He performed an independent verification

'

of the following prerequisites:

2.1.1.1 and 2.2.1.4 concerning Test

Record D.-awings being marked to show as built conditions and

acceptability of this by Engineering Design and Power Production,

'

-w

, . _ - - . . . . - . . - . - - . . - - . .

- --

'

.

N

.

.

RII Rpt. No. 50-327/79-02

I-4

-

2.1.1.2 concerning transfer of all necessary loads and electrical

boards to Power Production, 2.2.1.3 on most recent revision to

SOI 82.1 (Rev. 5) and SOI 57.4 (Rev. 4) being used; 2.2.1.7 on

differences in equipment configuration between preoperational

test TVA-13B(1) and this test, and 2.3.1.1 on Uncompleted Engineering

Change Notices to equipment operated during this test. No discrepancies

were noted during this review and verification.

The inspector witnessed the performance of the following tests

on diesel generator IA-A: Loss of Offsite Power (Non Accident);

Loss of Offsite Power followed by a Safety Injection; Simultaneous

Loss of Offsite Power and Safety Injection; Safety Injection

without Losing Offsite Power, and Simultaneous Safety Injection

and Loss of Offsite Power with ESF equipment aligned for full

flow conditions.

The inspector also monitored the performance

of Operations personnel in paralleling the shutdown boards

with the Offsite Power Bus and transfering the boards back to

their normal configuration in accordance with S01-82.1.

The

inspector had no comments on the conduct of the test.

6.

Plant Tour

The inspector toured portions of the turbine building, the control

bay and auxiliary instrument room, the auxiliary equipment building,

and the Unit No. I reactor containment.

Housekeeping and general

cleanliness were observed. No deficiencies were identified.