Forwards IE Insp Rept 50-327/79-02 on 790103-05.No Noncompliance Noted
ML19281A420
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 01/25/1979
From: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Niav Hughes
TENNESSEE VALLEY AUTHORITY
Shared Package
ML19281A421 List:
References
NUDOCS 7903130206
Download: ML19281A420 (2)


See also: IR 05000327/1979002

Text

~~

.

.

,

..

.

,she

.

f(p@* "84

9

xUNITED STATES

jo,

NUCLEAR REGULATORY COMMISSIOb8

h-8dP7

I

REGloN il

E

to1 MARIETTA STREET, N.W.

  • - -

,:

'

ATLANTA, GEORGIA 3o3o3

o

N H TN M

_

,,,,,

In Reply *-fer To:

RII:TJD

50-327/79-2

Tennessee Valley Authority

Atta: Mr. N. B. Hughes

Manager of Power

830 Power Building

Chattanooga, Tennessee 37401

Gentlemen:

This refers to the inspection conducted by Mr. Thomas J. Donat of this

office on January 3-5, 1979 of activities authorized by NRC License

Number CPPR-72 for the Sequoyah, Unit 1 facility, and to the discussion

of our findings held with Mr. W. F. Popp at the conclusion of the

inspection.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report. Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncocpliance were

disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice",

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public

Document Room.

If this report contains any information that you (or

your contractor) believe to be proprietary, it is necessary that you

make a written application within 20 days to this office to withhold

such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is

claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained

in a separate part of the document.

If we do not hear from you in this

,

regard within the specified period, the report will be placed in the

Public Document Room.

700313 0 Ao/f

i.. _ ._

._

_

..

..

.

.

Tennessee Valley Authority

-2-<

JAN 2 51979

-

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

[.C.

, Gc

}

F. J.

ong, Chief

/

Reactor Operations and

Nuclear Support Branch

Enclosure:

Inspection Report No. 50-327/79-2

cc w/ enclosure:

Mr. J. E. Gilleland

Assistant Manager of Power

830 Power Buildieg

Chattanooga, Tennessee 37401

Mr. G. G. Stack, Project Manager

Sequoyah Nuclear Plant

Post Office Box 2000

Daisy, Tennessee 37319

Mr. J. M. Ballentloe

Plant Superintendent

Sequoyah Nuclear Plant

Post Office Box 2000

Daisy, Tennessee 37319

Mr. J. F. Cox

400 Commerce Street

W9D214

Knoxville, Tennessee 37902

!