UNITED STATES

o

8

NUCLEAR REGULATORY COMMISSION

o

e

REGION 11

g

a'#

101 MARIETTA ST., N.W.. SUITE 3100

\\.....

ATLANTA, GEORGIA 30303

AUG 311979

In Reply Refer To:

RII:EJV

50-321/79-26

50-366/79-30

Georgia Power Company

ATTN:

J. H. Miller, Jr.

Executive Vice President

270 Peachtree Street

Atlanta, GA 30303

Gentlemen:

This refers to the inspec tion conducted by E. J. Vallish of this office on

August 15-17, 1979, of activities authorized by NRC Operating License No. DPR-57

and License No. NFP-5 for t'he Hatch facility, and to the discussion of our

findings held with T. V. Green at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is claimed that

the information is proprietary, and should be prepared so that proprietary

information identified in the application is contained in a separate part of the

document. If we do not hear from you in this regard within the specified period,

the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

'

,

Charles E. Murp y,

ief

Reactor Construction and Engineering

Support Branch

Enclosure:

See Page 2

1184

275

Y

791018o 058

~~' }

.~7; ~

-

,

,+

.

AUG 311979

Georgia Power Company

-2-

.

Enclosure:

Inspection Report Nos. 50-321/79-26

and 50-366/79-30

cc w/ enc 1:

M. Manry, Plant Manager

P. O. Box 442

Baxley, GA 31513

C. E. Belflower

Site QA Supervisor

P. O. Box 442

Baxley, GA 31513