Forwards IE Insp Rept 50-369/78-42 on 781205-08 & Notice of Violation
ML19273B165
Person / Time
Site: McGuire Duke Energy icon.png
Issue date: 12/26/1978
From: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parker W
DUKE POWER CO.
Shared Package
ML19273B150 List:
References
NUDOCS 7902060429
Download: ML19273B165 (2)


See also: IR 05000369/1978042

Text

e

.

.

[pigRREGuy),

UNITED STATES

NUCLEAR REGULATORY COMMISSION

,

,

{

g

REGloN ll

-

E

101 M ARIETTA STREET, N.W.

[

ATLANTA, GEORGIA 30303

o

  • %.....+*~

DEC 2 61978

In Reply Refer To:

RII:WTC

50-369/78-42

Duke Power Company

ATTN:

Mr. William O. Parker, Jr.

Vice President, Steam Production

Post Office Box 33189

422 South Church Street

Charlotte, North Carolina 28242

Gentlemen:

This refers to the inspection conducted by Mr. W. T. Cottle of this

office on December 5-8, 1978 of activities authorized by NRC Construction

Permit No. CPPR-83 for the McGuire Unit No. I facility, and to the

discussion of our findings held with Mr. T. McConnell at the conclusion

of the inspection.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report. Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observations by the inspector.

During the inspection, it was found that certain activities under your

license appear to be in noncompliance with NRC requirements. This item

and references to pertinent requirements are listed in the Notice of

Violation enclosed herewith as Appendix A.

This notice is sent to you

pursuant to the provisions of Section 2.201 of the NRC's " Rules of

Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201

requires you to submit to this office, within 20 days of your receipt of

this notice, a written statement or explanation in reply including:

(1)

corrective steps which have been taken by you, and the results achieved;

(2) corrective steps which will be taken to avoid further noncompliance;

and (3) the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that you (or your contrac-

tor) believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such information

from public disclosure. Any such application must include a full state-

ment of the reasons on the basis of which it is claimed that the informa-

tion is proprietary, and should be prepared so that proprietary informa-

tion identified in the application is contained in a separate part of

the document.

If we do not hear from you in this regard within the

specified period, the report will be placed in the Public Document Room.

7 9 0 2 0 6 0 4 ;tct

.

Duke Power Company

-2-

DEC I 61978

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

C

deu c

F. J. Long, Chief

Reactor Operations and

Nuclear Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report No. 50-369/78-42

cc w/ enclosures:

Mr. M. D. McIntosh, Plant Manager

McGuire Nuclear Station

Post Office Box 488

Cornelius, North Carolina 28031

Mr. J. C. Rogers, Project Manager

McGuire Nuclear Station

Post Office Box 33189

Charlotte, North Carolina 28242