Forwards IE Bulletin 79-01, Environ Qualification of Class IE Equipment. W/List of 11 Systematic Evaluation Program Plants for Which No Action Is Required
ML19270F689
Person / Time
Site: Catawba, Perkins, Cherokee  Duke Energy icon.png
Issue date: 02/09/1979
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Dail C
DUKE POWER CO.
References
NUDOCS 7903080552
Download: ML19270F689 (2)


Text

S

]

  1. R800 UNITED STATES 9'o,,

NUCLEAR REGULATORY COMMISSION REGION il

)e g

u 5

101 M ARIETTA STRE ET, N.W.

ATLANTA, GEORGI A 10303 1 /

FEB BM In Reply Refer To:

RII:JPO 50-413, 50-414 50-491, 50-492 and 50-493 50-488, 50-489 and 50-490 Duke Power Company Attn:

Mr. L. C. Dail, Vice President Design Engineering P. O. Box 33189 Charlotte, North Carolina 28242 Gentlemen:

Enclosed is IE Bulletin 79-01.

It requires action by you with regard to power reactor facilities with an operating license except for the 11 SEP plants which are listed in Enclosure 3.

This Bulletin is also being sent for information to the 11 SEP plants and all power reactor facilities with a construction permit. No action or written response is required for construction permit facilities or the 11 SEP plants.

Should you have questions regarding this Bulletin or the actions required of you, please contact this office.

Sincerely, k

. James P. O'Reilly MDirector

Enclosures:

1.

IE Bulletin No. 79-01 2.

List of IE Bulletins Issued in the past 12 months 3.

List of SEP Plants (11) 7903080 N

i Duke Power Company cc w/ enc 1:

Mr. J. T. Moore, Proj ect Manager Ctserokee Nuclear Station P. O. Box 422 Caffney, South Carolina 29340 Mr. D. G. Beam, Project Manager Catawba Nuclear Station P. O. Box 223 Clover, South Carolina 2971'

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 February 8, 1979 IE Bulletin No. 79-01 ENVIRONMENTAL QUALIFICATION OF CLASS IE EQUIPMEhT Description of Circumstances:

The intent of IE Circular 78-08 was to highlight to all licensees important lessons learned from environmental qualification deficiencies reported by individual licencees.

In this regard, licensees were requested to examine installed safety-related electrical equipment and determine that proper documentation existed which provided assurance that this equipment would function under postulated accident conditions.

The scope of IE Circular 78-08 was much broader than other previously issued Bulletins and Circularr (such as IEB 78-04 and IEB 78-02) which addressed specific component failures. The intent of this Bulletin is to raise the threshold of IE Circular 78-08 to the level of a Bulletin; i.e., action requiring a licensee response.

Inspections conducted to date by the NRC of licensees' activities in response to IE Circular 78-08 have identified one component which licensees have found to be unqualified for service within the LOCA environment.

Specificially, unqualified stem mounted limit switches (SMLS), other than those identified in previously issued IE Bulletin 78-04, were found to be installed on safety-related valves inside containment at both Duane Arnold and Quad Cities 1 and 2 Nuclear Generating Stations. The unqualified switches are identified as NAMCO Models SL2-C-11, S3CHL, sal-31, sal-32, D1200j,

EA-700 and EA-770 switches. According to the manufacturer, these switches are designed only for general purpose applications and are not considered suitable devices for service in the LOCA environment. Consequently, switches are being replaced at the above power plants with qualified components.

Also, NRC inspection of component qualification has identified equipment which does not have documentation indicating it is qualified for the LOCA environment. The inspections have also identified that the licensees' re-review and resolution of problem areas are not receiving the level of attention from all licensees which the NRC believes is warranted.

Because of the protracted schedule for completion of the re-review, we are now requesting the power reactor facilities with operating licenses to expedite completion of their re-review program originally requested by IE Circular 78-08 dated May 31, 1978.

Page 1 of 3 00Pc,e 7902120215