ML19270F045
| ML19270F045 | |
| Person / Time | |
|---|---|
| Site: | South Texas |
| Issue date: | 12/21/1978 |
| From: | Seidle W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Eric Turner HOUSTON LIGHTING & POWER CO. |
| Shared Package | |
| ML17195A451 | List: |
| References | |
| NUDOCS 7901250082 | |
| Download: ML19270F045 (2) | |
See also: IR 05000498/1978017
Text
hiiEL
[pa nrog .
UNITED STATES
' b
.
o
NUCLEAR RFGULATORY COMMISSION
e
' ' '
REGION IV
h ,, ,b - .
G11 RYAN PLAZA DRIVE, SUITE 1000
- (
f
ggm
.#
++***
December 21, 1978
In Reply Refer To:
RIV
Docket tio. 50-498/Rpt. 78-17
50-499/Rpt. 78-17
Houston Lighting and Power Company
ATTN:
Mr. E. A. Turner, Vice President
Power Plant Construction and
Technical Services
Post Office Box 1700
Houston, Texas
77001
Gentlemen:
This refers to the inspection conducted by Messers. W. G. Hubacek and
D. P. Tomlinson of our staff during the period December 5-8,1978, of
activities authorized by NRC Construction Permit Nos. CPPR-128 and
129 for South Texas Project, Units No.1 and 2, and to the discussion
of our findings with Mr. T. D. Stanley and other members of your staff
at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in
the enclosed inspection report.
Within these areas, the inspection
consisted of selective examination of procedures and representative
records, interviews with personnel, and observations by the inspectors.
Within the scope of the inspection, no items of noncompliance were
identified.
We have also examined actions you have taken with regard to previously
identified inspection findings.
The status of these items is identified
in paragraph 2 of the enclosed report.
During the inspection, it was found that certain of your activities
appeared to deviate from corr.nitments in the PSAR. This item and ref-
erences to the specific commitments are identified in the enclosed
Notice of Deviation. Please provide us within 30 days, in writing,
with your conments concerning this item, a description of any steps
that have been or will be taken to correct it, a description of any
steps that have been or will be taken te prevent recurrence, and
the date all corrective actions or preventive measures were or will
be completed.
7901250CG 1
g
.
,.
,
Houston Lighting and Power
Company
-2-
December 21, 1978
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part
2, Title 10, Code of Federal Regulations, a copy of this letter and the
enclosed inspection report will be placed in the NRC's Public Document
Room.
If the report contains any information that you believe to be
proprietary, it is necessary that you submit a written application to
this office, within 20 days of the date of this letter, requesting that
such information be withheld from public disclosure.
The application
must include a full statement of the reasons why it is claimed that the
information is proprietary. The application should be prepared so that
any proprietary information identified is contained in an enclosure to
the application, since the application without the enclosure will also
be placed in the Public Document Room.
If we do not hear from you in
this regard within the specified period, the report will be placed in
the Public Document Room.
Should you have any questions concerning this inspection, we will be
pleased to discuss them with you.
Sincerely,
(
f /" k'
I
j
f/fW. C. Seidle, Chief
/
Reactor Construction and
Engineering Support Branch
Enclosures:
1.
Appendix A, Notice of Deviation
2.
IE Inspection Report No. 50-498/78-17
50-499/78-17