Forwards IE Insp Rept 50-334/78-31 on 781101-06 & 1208.No Noncompliance Noted
ML19269D226
Person / Time
Site: Beaver Valley
Issue date: 01/16/1979
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Dunn C
DUQUESNE LIGHT CO.
Shared Package
ML19269D227 List:
References
NUDOCS 7903070503
Download: ML19269D226 (2)


See also: IR 05000334/1978031

Text

TBc4

..

.

.

  • *%

UNITED STATES

4

NUCLEAR REGULATORY COMMISSION

.,f'

REGION I

,

  • .

t

531 PARK AVENUE

KING OF PRU'SSI A. PENNSYl.,VANI A 19406

Docket No. 50-334

Duquesne Light Company

ATTN:

Mr. C. N. Dunn

Vice President

Operations Division

435 Sixth Avenue

Pittsburgh, Pennsylvania 15219

Gentlemen:

Subject:

Inspection 50-334/78-31

This refers to the inspection conducted by Mr. J. E. Kohler of the NRC

Region III office on November 1-6, December 8,1978, at Beaver Valley

Power Station, Shippingport, Pennsylvania, of activities authorized by

NRC License No. DPR-66 and to the discussions of our findings held by

Mr. Kohler with Mr. J. Werling and other members of your staff at the

conclusion of the inspection.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such information

from public disclosure. Any such application must be accompanied by an

affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement

of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b)(4) of Section

2.790.

The information sought to be withheld shall be incorporated as

far as possible into a separate part of the affidavit.

If we do not

hear from you in this regard within the specified period, the report

will be placed in the Public Document Room.

7903070 60 3

.

<.

Duquesne Light Company

2

16 JAN 1379

No reply to this letter is required; however, if you should have any

questions concerning this inspection, we will be pleased to discuss them

with you.

Sincerely,

c

E d n v_j. Brunner, Chief

Redctor Operations and Nuclear

f upport Branch

5

Enclosure: Office of Inspection and Enforcement Inspection

Report Number 50-334/78-31

cc w/ encl:

F. Bissert, Technical Assistant Nuclear

R. Washabaugh, QA Manager

J. Werling, Statior Superintendent

G. Moore, General Superintendent, Power Stations Department

J. J. Carey, Nuclear Technical Assistant