Forwards IE Insp Rept 50-369/78-39 on 781107-09,13-15.No Noncompliance Noted
ML19269C380
Person / Time
Site: McGuire Duke Energy icon.png
Issue date: 01/18/1979
From: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parker W
DUKE POWER CO.
Shared Package
ML19269C377 List:
References
781226, NUDOCS 7902020037
Download: ML19269C380 (2)


See also: IR 05000369/1978039

Text

I

.

[ p* 88Guq(o

UNITED STATES

NUCLEAR REGULATORY COMMISSION

a

3

HEGION il

.g

g

!

<

g

101 M ARIETT A sTRE ET, N.W.

  • 4

' 8

ATL ANTA. GEORGI A 30303

\\,

/

.....

DEC C 61978

In Reply Refer To:

RII:MCA

50-369/78-39

Dub Power Company

Attn: Y William O. Parker, Jr.

Viu President, Steam Production

P. O. Box 338

422 South Church Street

Charlotte, North Carolina

28242

Gentlemen:

This refers to the inspection conducted by Mr. M. C. Ashenden and others of

this office on November 7-9, 13, 14 and "

1978, of activities authorized by

NRC Construction Permit No. CPPR-83 for the McGuire Nuclear Station Unit 1,

Cornelius, North Carolina and company offices, Charlotte, North Carolina

facilities, and to the discussion of our findings held with Mr. M. D. McIntosh,

Mr0uire Station Manager and Mr. J. R. Wells, Duke Power Company QA Manager at

the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

sele:tive examinations of procedures and representative records, interviews

with personnel, and observations by the inspectors.

Within the scope of this inspection, no items of noncompliance were disclosed.

This office will not be able to verify implementation of the approved Quality

Assurance Program for Operations until the thirty items identified in the

enclosed report are corrected or further evaluation has been conducted.

These corrective actions or forther evaluations will be

eviewed during a

subsequent inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room. If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application

ithin 20

days to this office to withhold such information from public disclosure. Any

such application must include a full statement of the reasons on the basis of

which it is claimed that the information is proprietary, and abould be prepared

so that proprietary information identified in the application is contained in

a separate part o: the document. If we do not hear from you in this regard

within the specified period, the report will be placed in the Public Document

Room.

y902020 E7

.

.

.

Duke Power Corepany

-2-

DEC 2 61978

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

Y[

.frv

Osw

F. J. Long, Chief

Reactor Operations and

Nuclear Support Branch

Enclosure:

Inspection Report No.

50-369/78-39

cc w/ enc 1:

Mr. M. D. McIntosh, Plant Manager

McGuire Nuclear Station

P. O. Box 488

Cornelius, North Carolina 28031

Mr. J. C. Rogers, Project Manager

McGuire Nuclear Station

P. O. Box 33189

Charlotte, North Carolina 28242