ML19263E690

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-498/79-04 & 50-499/79-04 on 790320-23. Noncompliance Noted:Failure to Follow Concrete Placement Procedures
ML19263E690
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 04/11/1979
From: Gilbert L, Randy Hall, Hubacek W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19263E683 List:
References
50-498-79-04, 50-498-79-4, 50-499-79-04, 50-499-79-4, NUDOCS 7906250051
Download: ML19263E690 (8)


See also: IR 05000498/1979004

Text

.

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION IV

Report No. 50-498/79-04; 50-499/79-04

Docket No. 50-498; 50-499

Category A2

Licensee: Houston Lighting & Power Company

Post Office Box 1700

Houston, Texas

77001

Facility Name:

South Texas Project, Units 1 & 2

Inspection at: South Texas Project, Matagorda County, Texas

Inspection conducted: March 20-23, 1979

Inspectors:84 f,7k,(I/hd

/ /[77

W. G. Hubacek, Reactor Inspector, Projects Section

Date

(Paragraphs 1, 2, 3, 4, 5, 6 & 11)

  • ////l79
x

h L. D. Gilbert, Reactor Inspector, Engineering

Date

U

Support Section (Paragraphs 9 & 10)

Y//rl79

~

R. E. Hall, Chief, Engineering Support Section

Date

(Paragraphs 2,7&8)

Approved:

V////7 9

-u

W. A. Crossman, Chief, Projects Section

Date

Yf//f79

hR.E. Hall, Chief,EngineeringSupportSection

= _ -

Date

2217

354

79062500 N. k

Inspection Summary:

Inspection on March 20-23, 1979 (Report No. 50-498/79-04; 50-499/79-04)

Areas Inspected:

Routine, unannounced inspection of construction activi-

ties including observation of work related to concrete placement for Unit 2;

review of r cords related to welding of the Unit 1 containment liner dome;

review of '.sbrication records related to the Unit 1 crane girder; review of

receivint records for electrical components; review of reported 50.55(e)

items; and review of previous inspection findings.

The inspection involved

seventy-five inspector-hours by three NRC inspectors.

Results: Of the six areas inspected, one apparent item of noncompliance

was identified in one area (infraction - failure to follow concrete place-

ment procedures - paragraph 7).

2217

355

9

-2-

.

DETAILS

1.

Persons Contacted

Principal Licensee Employees

  • T. R. Alford, Project Site Manager
  • T. D. Stanley, Project QA Supervisor
  • L. D. Wilson, Site QA Supervisor
  • D. G. Long, Lead Engineer
  • T. J. Jordan, Lead Engineer

M. H. Smith, Plant QA Supervisor

  • R.

L'. Ulrey, QA Specialist

  • D. W. Bohner, QA Specialist
  • M. S. Monteith, QA Technician

C. L. Grosso, Associate Engineer

M. M. Johnsun, Senior Engineer

Other Personnel

  • J. Dodd, Senior Manager of Construction, Brown & Root (B&R)
  • J. H. Pepin, Project General Manager, B&R
  • C. W. Vincent, Project QA Manager, B&R
  • G. T. Warnick, Site QA Manager, B&R
  • J. R. Monroe, Construction Project Manager, B&R
  • S. A. Rasnick, Construction Chief Engineer, D&R
  • A. Smith, Chief Construction Quality Engineer, B&R

G. Ewert, Internal Surveillance Supervisor, B&R

R. Allgood, Training Coordinator, B&R

K. E. Easter, External Surveillance, B&R

T. J. Foley, Site QA Manager, Pittsburgh Des Moines (PDM)

The IE inspectors also interviewed other licensee and contractor

employees including members of the QA/QC and engineering staffs.

  • denotes those attending the exit interview.

2.

Licensea Action on Previous Inspection Findings

.

(0 pen) Infraction (50-498/78-16; 50-499/78-16):

Failure to Provide

Procedure for Housekeeping Inspection. The IE inspector reviewed

corrective actions described in the licensee's letters, dated

January 8,1979, and February 14, 1979.

Corrective actions have

been accomplished as described in the letters; however, Procedure

2217

356

-3-

GCP-4, " Housekeeping," Rev. 2, dated December 15, 1978, did not

sufficiently define responsibilities for planning and implementa-

tion of housekeeping requirements as required by ANSI N45.2.3.

In addition, the requirements for Safety Department inspection

of Zone IV and V areas were not sufficiently defined.

The

above concerns were also identified in a Brown & Root (B&R)

QA housekeeping surveillance report, dated March 22, 1979.

This

matter will remain open pending completion of corrective action

in response to the B&R surveillance report.

(0 pen) Unresolved Item (50-498/79-02; 50-499/79-02): Qualifi-

cation Requirements for Cadwelders. Brown & Root Quality Control

Procedure CCP-ll is undergoing revision to define Cadwelder

qualification requirements consistent with Regulatory Guide 1.10.

This item will remain open pending review of the revised and

approved procedure.

3.

Site Tour

The IE inspectors toured various areas of the site to observe con-

struction activities and to inspect housekeeping and equipment

storage.

No items of noncompliance or deviations were identified.

4.

Review of Items Reported Under 50.55(e)

The IE inspector reviewed the status of the following items which

were previously reported under 10 CFR 50.55(e):

a.

Voids in Lift 15 of the Unit 1 Reactor Containment Building (RCB)

The IE inspector was informed that grouting of voids in lift 15

of the RCB was completed on March 1,1979.

Preparations were

under way for load testing of the polar crane bracket located at

2150 azimuth which was chosen as the representative bracket for

the test. A maximum load of 375 tons will be applied at a

distance of 2'8" from the liner surface.

Loading and unloading

will be in established increments.

Deformation measurements will

be made by means of deflection gages and strain rosettes. The

deformation measurements will be used to evaluate the strain

recovery process during the unloading cycle.

This matter vill be reviewed during a subsequent inspection

following s.bmission of the final report.

2217 357

-4-

.

b.

Installation of Anchor Bolts Fabricated from the Wrong Material

Nonconformance Reports (NCR) S-M1080 and S-M1080A identify anchor

bolts which were fabricated from carbon steel of the wrong grades

(A36 and A193). Materials have been identified as to what was

required and what was actually used in fabrication of the bolts.

Locations where the anchor bolts have been embedded in concrete

have been identified.

The IE inspector was informed that B&R

design engineering will disposition the bolts on a case by case

basis and they will be replaced as required.

No items of noncompliance or deviations were identified.

5.

NSSS Component Supports

The IE inspector was informed that eighteen of twenty-eight vertical

~ columns, which will be located at elevation (-)ll'-3 to 16'0" in the

Unit 2 RCB, will be fabricated on site by PDM. ~ Preliminary work will

be performed in PDM's Des Moines facility with completion of the

fabrication to be accomplished in the existing fabrication shop at

the site. The remaining ten columns will be fabricated by LAMCO.

This change was stated to be necessary due to construction scheduling

requirements which require delivery of the columns in July 1979.

The IE inspector was also infomed that laminations have been detected

in nine transition pieces for Unit 1 NSSS component upper and lower

lateral supports. The laminations were found by UT at the vendor's

shop.

Eight of the transition pieces are presently located at the

vendor's shop and will be repaired by the vendor.

The remaining

transition piece located at the site will be evaluated by the licen-

see and Brown & Root engineering.

No items of noncompliance or deviations were identified.

6.

Review of Receiving Records

The IE inspector reviewed receiving records for electrical components

to ascertain whether requirements of Procedure GCP-22, " General

Material Receiving and Storage," were met.

Records for the Flux

Mapping Console, Boron Recycle Panel, Rod Control System, and a

Containment Spray Pump. motor were reviewed.

No items of noncompliance or deviations were identified.

2217 358

-5-

.

7.

Observation of Concrete Placement

A portion of u ncrete placement ME2-W001-01, wall at the northwest

corner of Unit 2, Mechanical Electrical Auxiliary Building, was

observed for compliance with procedural requirements of :

QCP-A040KPCCP-3, "Prepour Activities," Rev. 9, dated

July 5, 1978 (CCP-3)

QCP-A040KPCCP-4, " Concrete Placement and Finishing,"

dated July 6, 1978 (CCP-4)

The Pour Card and Examination Checklists were revie-fad.

It was

verified that all required items had been signed by Construction,

Engineering and Quality Control. The pour card was signed author-

izing start of the placement.

.

The forms were inspected by the IE inspecto:- and found to be clean

and free of debris. The surface of the construction joint was

observed to be in the saturated surface dry ' condition, s.mept that

the IE inspector observed pools of standing water in the region

between the interior wall forms and the in-place water stop on the

construction joint surface. These pools covered approximately 70%

of the length of the placement and were measured to be 1/2 inch

deep in one location. The QC inspector and B&R foreman indicated

their intent to " walk" the water ahead of the first layer of concrete

to remove it. Brown and Root Procedure CCP-3, paragraph 3.35.9

stipulates that standing water would be removed from the area of

placement in construction joints. When the IE inspector noted that

te placement crew was not " walking" the water out of the placement,

the QC inspector stopped the work until air hoses could be provided.

Subsequently the standing water was removed ahead of concrete place-

ment using the air hoses and brooms.

During placement of the first layer of concrete, two cases were

noted in which the vibrators were used 'to move placed concrete

lateral distances of 8 and 10 feet from the discharge point.

Brown

and Root Procedure CCP-4, paragraph 3.5.3 restricts lateral movement

of concrete to less than five feet.

Initiation of concrete place-

ment with standing water on the construction joint and the noted

lateral movement of concrete with vibrators appear to be examples

of failure to follow procedures as required by Criterion V of

Appendix B to 10 CFR 50.

During the placement, a rainstonn occurred. As specified in para-

graph 3.4.1 of CCP-4, placement was stopped until rain protection

'

could be provided. During erection of rain protection, rain water

accumulated on the surface of the recently placed concrete. After

2217 359

-6-

~

.

the rain stopped, placement was resumed after inspection by Engineering

and Quality Control. An NCR was initiated to confirm that the maximum

allowable water / cement ratio was not exceeded by the rainwater which

was added to the concrete. After resumption of placement, the IC

inspector verified that previously placed concrete was still in the

plastic state as required by paragraph 3.4.3 of CCP-4.

After completion of the placement, it was verified that the surface

of the concrete was adequately protected and that the water-stop was

installed.

8.

Miscellaneous

During the inspection and by telephone on March 26,1979, the IE

inspector explored the circumstances surrounding an altercation

between a quality control inspector and a construction engineer.

It was determined that management response to this matter had been

timely and effective in indicating support for the site quality

assurance program. No long range adverse effects were identified.

No items of noncompliance or deviations were identified.

9.

Containment Liner Dome

a.

Observation of Work

The IE inspector observed shielded metal-arc welding of Seam 25

and Seam Sl-13B on Course Assembly 1 for the Unit 1 Containment

Dome. The qualification and/or cartification documentation by

PDM was reviewed for the two weldeas and E7018 welding electrode

being used for welding the two seans.

In the areas inspected,

no discrepancies were noted between the documentation and the

requirements of Section III or IX of the ASME B&PV Code.

b.

Review of Records

The IE inspector selectively reviewed the completed documentation

for three seam welds on the Unit 1 Containment Liner D.ome Course

Assemblies. The seam welds were identified as Seam 21 of Course

2, Seam 22 of Course 3 and Seam 14 of Course 4.

The documentation

for each seam weld was reviewed for completeness and use of quali-

fied welders, certified welding electrode, certified nondestructive

2217 360

-7-

..

-

examination reports, and qualified examination personnel.

In the

areas inspected, no discrepancies were noted between the documen-

tation and the requirements of Section III, V or IX of the ASME

B&PV Code.

No items of noncompliance or deviations were identified.

10.

Polar Crane Girders

The IE inspector selectively reviewed the shop fabrication records and

material certification reports for the Unit 1 Crane Girder, Pc 125G2

of Drawing 125AG, Revision C.

The girder steel plate material was

certified as conforming to the ASTM A537 Class 1 specification for

chemical and mechanical properties. The gusset and backing bar materials

were certified as conforming to the ASTM A36 specification for chemical

and mechanical properties.

In the areas inspected, no discrepancies

were noted-between the PDM shop fabrication record and material cartifi-

cation reports for the crane girder and the B&R specification 2C2695S006,

Revision G, " Steel Liner Work for Reactor Containment Structures."

No items of noncompliance or deviations were identified.

11.

Exit Interview

The IE inspectors met with licensee representatives (denoted in para-

graph 1) at the conclusion of the inspection on March 23, 1979.

The

IE inspectors summarized the purpose and the scope of the inspection

and the findings. A licensee representative acknowledged statements

of the IE inspector concerning the item of noncompliance.

.

2217

361

-8-