ML19263B546

From kanterella
Jump to navigation Jump to search
Forwards Insp Rept 50-333/78-21 on 780925-28 & Notice of Violation
ML19263B546
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 10/30/1978
From: Galen Smith
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Leonard J
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
Shared Package
ML19263B540 List:
References
NUDOCS 7901180373
Download: ML19263B546 (2)


See also: IR 05000333/1978021

Text

.-

's

[

0%

UNITED STATES

4

g

g

NUCLEAR REGULATORY COMMisslON

y @ egfi S

nEcios i

$' f()/

E

631 PARx AVENUE

o

xiNo or Pnussi A, PENNSYLVANIA 19406

'

do*cl+et No. 50-333

OCT 3 01973

Power Authority of the State of New York

James A. FitzPatrick Nuclear Power Plant

ATTN:

Mr. J. D. Leonard

Resident Manager

P.O. Box 41

Lycoming, New York 13093

Gentlemen:

Subject:

Inspection 50-333/78-21

This refers to the inspection conducted by Mr. K. Plumlee of this office

on September 25-28, 1978, at the James A. FitzPatrick Nuclear Power

Plant, Scriba, New York, of activities authorized by NRC License No.

DPR-59 and to the discussions of our findings held by Mr. Plumlee with

yourself and others of your staff at the conclusion of the inspection,

and to a subsequent telephone discussion between Mr. Plumlee and Mr. A.

McKeen on October 3, 1978.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, measurements made by the inspector, and observations by the

inspector.

Based on the results of this inspection, it appears that certain of your

activities were not conducted in full compliance with NRC requirements,

'

as set forth in the Notice of Violation, enclosed herewith as Appendix

A.

These items of noncompliance have been categorized into the levels

as described in our correspondence to you dated December 31,197^.

This

notice is sent to you pursuant to the provisions of Section 2.20. of the

NRC's " Rules of Practice", Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to submit to this office, within twenty (20)

days of your receipt of this notice, a written sta tement or explanation

in reply including:

(1) corrective steps which have been taken by you

and the results achieved; (2) corrective steps which will be taken to

avoid further items of noncompliance; and (3) the date when full ccm-

pliance will be achieved.

790118037 3

,

.

,

Power Authority of the State of New York

,

2

Item number B, shown in the Notice of Violation enclosed with this

letter, is a recurrent or uncorrected item having occurred previously

during February and again during May of this year.

In your response

please give this matter your particular attention.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part

2. Title 10, Code of Federal Regulations, a copy of this letter and the

enclosures will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to

be proprietary, it is necessary that you make a written application

within 20 days to this office to withhold such information from public

disclosure. Any such application must be accompanied by an affidavit

executed by the owner of the information, which identifies the document

or part sought to be withheld, and which contains a statement of reasons

which addresses with specificity the items which will be considered by

the Commission as listed in subparagraph (b)(4) of Section 2.790.

The

information sought to be withheld shall be incorporated as far as

possible into a separate part of the affidavit.

If we do not hear from

you in this regard within the specified period, the report will be

placed in the Public Document Room.

Should you have any questions concerning this inspection, we will be

pleased to discuss them with you.

Sincerely,

pr

-

Geo ge If. Smith, Chief

Fue Facility and Materials Safety

B nch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement Inspection Report

Number 50-333/78-21

cc w/encls

George T. Berry, General lianager and Chief Engineer

P. W. Lyon, Manager - Nuclear Operations

A. Klausmann, Director, Quality Assurance

M. C. Cosgrove, Quality Assurance Supervisor

J. F. Davis, Chairman, Safety Review Committee

L. R. Bennett, Assistant General Manager - General Counsel

G. M. Wilverding, Licensing Supervisor